Doc No HEART-ALL-CON-BRF-001 Rev Rev.D Issue 30 September 2026 Page 1 of 1 Strictly Confidential
HEART HT
Preliminary Introduction — Post-NDA Disclosure

HEART Project · Hue High-Tech Park
AI Data Center & Robotics Infrastructure Platform

A 1,081 ha national-grade high-tech park in Hue City, Central Vietnam — anchored on a 1,000 MW-class AI data center campus and secured across five pillars: power on a 22→110→500 kV ladder, with the newly planned nearby 500 kV substation being moved inside the park under the PDP-8 amendment; cooling water of potable-source quality from a national-security hydropower dam ~5 km away, built and operating to the 1/1,000-year-flood first-class standard; connectivity from Viettel and VNPT at RTT ≤ 25 ms with two submarine landing points each; land on 50-year PPP-BOT and high-tech green-lane tenure; and talent — 1,000+ PhD-level professionals resident in the Hue–Da Nang semiconductor belt.

◉ Open the 3D Zone SimulatorInteractive land-use model — PK-1 to PK-5 on the actual terrain ↗
22→110→500 kV
POWER — 2×40 MW building (AIP) · 2×150 MW secured · 500 kV moved in-park (PDP-8) · time-to-power 2027
~5 km · 1/1,000-yr
WATER — national-security dam, potable-source quality · in-park 1/1,000-yr flood canal
≤25 ms · 2+2
CONNECTIVITY — Viettel & VNPT, 2 circuits & 2 submarine landing points each + land emergency route
50-yr × 2
LAND — national HTP: PPP-BOT infrastructure · high-tech green-lane AI DC
1,000+ PhD
TALENT — Hue–Da Nang semiconductor belt residents
Document Control
Document No.
HEART-ALL-CON-BRF-001-RevD
Revision
Rev.D — adds §17 AI DC Investor Incentives
Issue Date
30 September 2026
Language
English (controlling)
Prepared by
HEART High-Tech Joint Stock Company (HEART HT)
Prepared for
Prospective Delivery Partner — named recipient
Basis of issue
Executed Non-Disclosure Agreement
Classification
Strictly Confidential — named recipients only
Distribution
No onward distribution, reproduction or extraction
Status
For discussion — not a contractual document

01Executive Summary

The HEART Project is the development of the Hue High-Tech Park (Khu Cong nghe cao Thanh pho Hue) — a 1,081 ha multi-sector, open-format high-tech park in which a large-scale AI data center is the core infrastructure asset, not an ancillary component. This is the first master plan of its kind in Vietnam. This document is an infrastructure-focused introduction prepared for a prospective delivery partner following execution of the NDA.

The site’s merits, maximally compressed — five pillars
POWER
Supply secured on a three-level ladder: 22 kV — 2 × 40 MW allocated (AIP) and building now (+40 MW expandable); 110 kV — 2 × 150 MW, one immediate, one against demand-backed commitment; and under the PDP-8 amendment, the newly planned nearby 500 kV substation is being moved inside the park — the platform of a Giga-Scale Campus. The zone holds retailer standing under the DPPA decrees as a supplier that is also the anchor offtaker; time-to-power: 2027.
WATER
Stable cooling water of potable-source quality from a national first-class hydropower dam only ~5 km away — a Prime-Ministerial national-security installation (Decisions 124 & 166/QĐ-TTg) built and operating to the 1/1,000-year-flood first-class safety standard; inside the park, the AI-DC platform is protected by its own 1/1,000-year flood-prevention canal design.
CONNECTIVITY
Viettel and VNPT each: RTT ≤ 25 ms, ≥ 2 circuits each, 2 submarine landing points each — plus a terrestrial emergency route via five countries to a Malaysia–Singapore destination over one land landing-point circuit.
LAND
A national high-tech park under State establishment and city-government administration: infrastructure on a 50-year PPP-BOT; the AI DC on a 50-year high-tech green-lane track.
TALENT
Inside the Hue–Da Nang semiconductor belt and high-tech development corridor — 1,000+ PhD-level science-and-engineering professionals in residence.
AI DC investor incentives — the package in five lines
Detail → §17
TAX
CIT 10% for 15 years, 4 years exempt + 50% off for 9 — automatic for any new project in the park, no certificate needed; rising to 10% for 25 years once the operator is confirmed as a Group-1 high-tech or strategic-technology enterprise (CIT Law 67/2025; Law 133, Art. 25.7).
AI DC BY NAME
The High Technology Law names AI data center construction projects as eligible for the customs priority regime (Art. 25.5) — on the critical path for GPU, server, power and cooling imports; certified enterprises add a 5-year import-duty exemption on production and research inputs (Art. 25.6).
LAND COST
State land rent is exempt for the full lease term on area subleased to high-tech projects, and the developer may not price the exemption into the sublease (Decree 260, Art. 23.5) — the saving reaches the AI DC tenant.
SPEED
Most-favourable location tier (especially difficult socio-economic area) and one-stop handling; project confirmation by the park Management Board in 15 working days + 1 where no policy approval or IRC is needed (Decree 260, Art. 22, 28, 31).
PEOPLE
PIT exemption for high-tech personnel, including foreigners, visa and work-permit preferences for R&D staff, market-rate packages for leading experts, and up to 5 years of interest-rate support on qualifying R&D (Law 133, Art. 13, 16; Decree 260, Art. 4–5, 35–38).
Hue High-Tech Park — full-site phase division master plan (HHTP-P1-GL-001)
The site at a glance — 1,081 ha, three phases. Full-site phase division plan (drawing HHTP-P1-GL-001, September 2026, concept design): Phase 1.1 north-east adjoining the expressway axis · Phase 1.2 centre · Phase 2 south · Phase 3 west. Detail in §14 and §15.

1.1 What the project is

  • Location. Hung Loc Commune, Hue City, Central Vietnam — centroid 16.31441°N, 107.697017°E (WGS84); 4.29 km (E–W) × 5.38 km (N–S). Bounded north and east by the Cam Lo – La Son Expressway.
  • Statutory basis. Established under High Technology Law No. 133/2025/QH15 and Government Decree No. 260/2026/ND-CP dated 30 June 2026 (Articles 18, 19 and 20 governing the orientation, conditions and procedure for establishing a high-tech park).
  • Structure. Five functional zones (PK-1 to PK-5) plus protective green buffer and road reserve. PK-2 — the AI data center zone — is the single largest zone at 319.52 ha (29.56%). The data center is foundational AI-training and high-performance-compute infrastructure, not a storage-type facility (Report 25/2026).
  • Power. Ultimate envelope ~1,550 MW: approximately 1,000 MW AI data center load and 550 MW high-tech manufacturing, R&D and utilities. Delivery per the filed roadmap (Report 25/2026) — Phase 1.1 takes 40 MW from two independent 110 kV sources over the 22 kV grid, the following phase moves to 110–220 kV, and post-2030 the park connects at 500 kV through two in-project 500/220/110 kV substations of 2 × 900 MVA each, with ~300 m tie-lines lying entirely inside the site boundary. Should State and city objectives allow an earlier start, the Investor intends to accelerate this roadmap — the commitment package in §20.2 is engineered for early expansion. See §7–§8.
  • Water. 13,000 m³/day in Phase 1, rising to 100,000 m³/day in Phase 2, drawn from the Ta Trach reservoir under an existing surface-water licence and a project-specific written confirmation, with Truoi reservoir on an independent catchment as backup.
  • Flood safety — designed for the 1-in-1,000-year flood. The drainage and earthworks concept is engineered against an extreme flood of 1/1,000-year return period (drawing HHFP-P1-RWS-003), and an absolute zero-inundation performance guarantee for the data center platform is fixed as one of the project’s core technical conditions (§13.2, §18.4). The guarantee rests on four engineered layers: the flood-relief canal network, fully controlled cooling-water flow routing, the upstream Ta Trach dam — built to hydropower-dam design standards, a fundamentally higher structural class than ordinary irrigation reservoirs — and professional dam operation by the dedicated state-owned Ta Trach operator. 79.5% of the site already sits in the 5–30 m elevation band, well above regional flood levels.
  • Connectivity. Designed to TIA-942-C Rated-4: two independent submarine cable systems via separate landing stations (APG at Da Nang, SJC2 at Quy Nhon), diverse domestic routes from two carriers, a terrestrial Vietnam–Singapore route, and a carrier-neutral Meet-Me Room.
  • Delivery. Trunk infrastructure is to be procured as a PPP project under a 25–30 year BOT contract using no state capital, via the investor-appointment route under the PPP Law.

1.2 Why the site works for heavy digital infrastructure

Power at source
4 × 500 kV

The North–South 500 kV transmission corridor crosses the site — four 500 kV circuits plus two 220 kV circuits — allowing head-end substations to be built inside the park boundary (PK-4) rather than wheeled in over distance.

Water at source
420 × 10⁶ m³

Ta Trach reservoir, ~2 km from the boundary, licensed at 2.0 m³/s (~172,800 m³/day) for domestic and industrial supply — an independent surface source, not the municipal system.

Ground & climate
79.5%

Of the site sits in the 5–30 m elevation band on competent granite bedrock, with a bearing safety factor of 15–50× data center requirements. No geological faults cross the planning area.

Corrosion
> 20 km

Distance to the coast exceeds the ASHRAE A2 salt-corrosion threshold, avoiding special protection measures and reducing equipment maintenance cost by an estimated 15–20% over a 20-year life versus a coastal site.

Land assembly
~180

Households to be resettled (Ben Van, Duong Loc, Hoa Loc hamlets), on production forest with low settlement density — no mass relocation, and site formation cost that is marginal relative to comparable Vietnamese parks.

Flood design basis
1 / 1,000 yr

Zero inundation, guaranteed. Extreme-flood protection is designed to a 1/1,000-year return period — far beyond the 1/100-year basis typical of industrial parks — and absolute non-flooding of the data center platform is carried as a binding core technical condition, not a design aspiration — backed by flood canals, controlled cooling-water routing, the hydropower-dam-class Ta Trach dam and its professional state-owned operator.

Buildable area
700–800 ha

Of the 1,081 ha, roughly 700–800 ha is topographically straightforward to develop; the balance is upland and water body retained as landscape and robotics test terrain.

Basis of this document. All zoning areas, land-use ratios, load figures, phasing, cost and funding data in this document are taken directly from the project establishment report “De an thanh lap Khu Cong nghe cao Thanh pho Hue” (DT_BCTH_DeanKHCNHue, 12 July 2026). That report is the controlling reference; where this summary abbreviates, the report governs.

02Site & Regional Access

2.1 Boundary and dimensions

Site definition — per master plan
ParameterValue
Administrative locationHung Loc Commune, Hue City (south-east of Hue City centre)
Total planned area1,081 ha
Centroid16.31441°N, 107.697017°E (WGS84)
Dimensions4.29 km east–west × 5.38 km north–south
North & east boundaryCam Lo – La Son Expressway
South boundaryHung Loc Commune (remainder)
West boundaryPhu Bai Ward, Hue City
Readily buildable area≈ 700–800 ha
Park formatOpen type — no perimeter wall; boundary controlled by survey markers

2.2 Regional connectivity

NodeDistanceNotes
Phu Bai International Airport≈ 11 km9.7 km measured to the commune boundary. See §20 for the aviation-corridor item.
Hue City centre≈ 25 km—
Chan May Deep-Water Port≈ 50 kmPrincipal seaport for heavy and oversized deliveries.
La Son Industrial Park≈ 2 km301.16 ha approved 1/2,000 detailed plan; Zone 2 expansion of 225.6 ha approved by Decision 777/QD-UBND dated 7 Mar 2026.
High-speed rail alignment≈ 10 kmNational strategic railway project.
Road accessAdjacentProvincial Road 15B connects to TP 14B and National Highway 1A; direct access to the Cam Lo – La Son – Tuy Loan Expressway (La Son–Tuy Loan section, ~80 km Hue–Da Nang, being widened to four lanes).
Regional setting on satellite imagery — park position, trunk corridors and Da Nang landing station
Regional setting. The park’s position on satellite imagery (10 Sep 2026) with carrier trunk corridors and the link toward the Da Nang landing station (~85 km). The Cam Lo – La Son Expressway (CT01) bounds the park on the north and east; interchange delivery for super-heavy cargo is covered in §12.

2.3 Urban amenities and living environment

The park is not a greenfield in isolation: the civic amenities that international staff, engineers and relocating families require are already in place nearby, and the wider living and settlement environment is being actively upgraded by the City as part of the high-tech park programme.

Already in place — within daily reach

Airport. Phu Bai International Airport ~11 km — scheduled domestic and international services.  Healthcare. Hue Central Hospital — one of Vietnam’s three top-tier central hospitals — plus the Hue University of Medicine and Pharmacy hospital system.  Public security. Commune- and ward-level police and administrative services operate in Hung Loc and adjacent wards.  Education. Public schools serve the commune today, with Hue University — one of Vietnam’s major regional universities — anchoring the tertiary and STEM talent pipeline in the city.

Living & settlement conditions — being strengthened

A millennium heritage city. Hue is Vietnam’s ancient imperial capital; the Complex of Hue Monuments is a UNESCO World Heritage Site, and the city is one of the country’s premier tourism destinations.  Cost of living. Substantially lower than Hanoi or Ho Chi Minh City for housing, services and daily life.  Fresh local supply. Year-round fresh vegetables and fruit from the surrounding agricultural belt and daily fresh seafood from the coast and the Tam Giang lagoon system. The City is progressively upgrading housing, international schooling and lifestyle amenities as part of the settlement-environment programme accompanying the park.

2.4 Benchmark against Vietnam’s established high-tech parks

Comparison of high-tech parks — Central Vietnam and nationally (source report, 2026)
CriterionHue HTPDa Nang HTPHoa Lac HTPSHTP (HCMC)
Area (ha)1,0811,1281,586913
Land price (USD/m²)LowHighHighHigh
Power tariff (USc/kWh)Potentially lower with private power infrastructure~8–9~8–9~8–9
Distance to airport9.7 km17 km47 km18 km
Distance to seaport34.3 km25 km150 km10 km
Cooling waterTa Trach reservoir, confirmed at 100,000 m³/day ★LimitedLimitedLimited
Available power800 MW (Phase 1+2), targeting 1,550 MW cumulative by 2032LimitedLimitedLimited
Submarine cable80 km (Da Nang)0 km (direct)Long100 km (Vung Tau)
Note on distance figures. The benchmarking table above is reproduced verbatim from the source report and measures from the commune reference point; §2.2 measures from the park boundary. Both are retained rather than reconciled, so that the reader can trace each figure to its source.

03Zoning Framework — PK-1 to PK-5

The land-use balance below is the controlling zoning reference for the project. Every subsequent infrastructure figure in this document is sized against it.

General plan layout — Phase 1 · 156.7 ha. Conceptual master layout of the Hue Ci
General plan layout — Phase 1 · 156.7 ha. Conceptual master layout of the Hue City High-Tech Park showing developable parcels and the PK-1 to PK-5 zone framework that governs all subsequent infrastructure sizing.
PK-1 25.24%
PK-2 29.56%
PK-3
PK-4
PK-5 21.03%
GT
PK-1 R&D & Pilot Production PK-2 AI Data Center PK-3 Services & Amenities PK-4 Head-End Technical Infrastructure PK-5 Green / Water / Landscape Protective green buffer Roads
Land-use balance by functional zone — controlling reference
No.Zone / land categoryCodeArea (ha)Share (%)
PK-1High-tech R&D and pilot productionNC-SXTN272.0725.24
PK-2High-tech infrastructure (AI Data Center)HT CNC319.5229.56
PK-3High-tech services and amenitiesDVHH88.618.20
PK-4Head-end technical infrastructureHTKT28.982.68
PK-5Greenery – water bodies – landscapeCX, MN235.9321.03
6Protective green bufferCXCL19.011.76
7RoadsGT116.0810.74
TOTAL PLANNED AREA1,081100.00

3.1 Zoning principles

  • Functional coherence between R&D and pilot production; high-tech infrastructure (AI data center); services and amenities; head-end technical infrastructure; and green–water–landscape.
  • Statutory 15% cap on the services and amenities group (excluding technical infrastructure, greenery and water bodies) under Article 19(1)(d) of Decree 260/2026/ND-CP. At 8.20%, PK-3 is planned materially below the cap.
  • High allocation to green and water — PK-5 plus the buffer is 22.79% of the site — supporting microclimate regulation and landscape integration, and excluded from the 15% service cap.
  • Residential accommodation sits outside the park boundary. Long-term worker and expert housing is planned adjacent to or surrounding the park under Articles 19(1) and 24 of Decree 260/2026/ND-CP. Only short-stay accommodation directly serving high-tech operations is permitted inside the boundary (Article 30).
  • Each zone is subdivided into coded functional lots with individual land-use parameters, giving flexibility in investment attraction and phased delivery.

04PK-1 — R&D and Pilot Production · 272.07 ha

PK-1 is the knowledge and prototyping core of the park. The zone is deliberately designated “pilot production” rather than “industrial production”: under High Technology Law 133/2025/QH15 the park prioritises research, technology mastery and controlled testing, and does not host purely commercial-scale industrial manufacturing within its boundary.

a) Advanced research centres

  • IT laboratories — AI, machine learning, IoT, information security, semiconductor IC design
  • Biotechnology laboratories — genomics, recombinant proteins, next-generation vaccines, crop and livestock genetics, biofuels
  • High-tech and strategic-technology R&D centres
  • New materials, nanomaterials and semiconductor materials laboratories
  • High-tech medical and pharmaceutical applications centre, in cooperation with Hue Central Hospital and Hue University of Medicine and Pharmacy

b) Incubation and acceleration

  • Technology start-up incubator with shared laboratories, office space and mentoring
  • Accelerator for commercialising Hue University research outputs
  • Co-working space and fab lab for the innovation community

c) High-tech workforce training

  • Joint training centre with Hue University — AI, semiconductor and robotics engineering
  • Vocational centre — cleanroom technicians, high-tech equipment operators
  • International training centre linked to institutions in Japan, Korea and Taiwan (semiconductors and AI)

d) / e) Applied technology and pilot manufacturing (289.4 ha)

  • Microelectronics and semiconductor pilot line — cleanrooms class 100–10,000, chemical handling systems, ultrapure water (UPW)
  • Electronic components, sensors and IoT devices pilot production
  • Robotics and automation equipment pilot production — industrial robots, service robots, AGVs
  • High-tech pharmaceuticals — GMP-WHO compliant plant
  • High-tech medical devices — diagnostic and therapeutic equipment, high-grade consumables
  • New materials — composites, polymers, nano and semiconductor materials
  • Technology transfer centre bridging research and production

f) International AI Robot Certification Center

A dedicated testing and certification capability for robotics and AI products — the first of its kind planned in Vietnam, and a differentiator for tenants who require in-country conformity assessment.

g) Mountain Robot Test Bed

Located on the upland portion of the site with natural vegetation retained. Field testing for autonomous and field robots, unmanned ground vehicles (UGV/AGV), and localisation, navigation, sensing and recognition algorithms in unstructured environments — slope, canopy occlusion, rough terrain. Simultaneously performs microclimate and landscape functions.

g) River Robot Test Bed

Riparian green corridor plus the river water body as a test range for underwater and surface autonomous vehicles (AUV/ASV), hydrological technology, environmental sensing and water-quality monitoring. Complements the mountain test bed and provides ecological amenity for the working population.

Construction implication. PK-1 contains the technically demanding building types in the programme — class 100–10,000 cleanrooms, UPW plant, chemical distribution, GMP-WHO pharmaceutical process areas and vibration-sensitive laboratories — alongside conventional office and training buildings. These are the packages where international delivery expertise is most directly relevant.

05PK-2 — AI Data Center Zone · 319.52 ha · the anchor

PK-2 is the largest zone in the park and its economic anchor. The AI data center is classified as technology infrastructure — computing and data infrastructure, digital platform and controlled test environment — and not as social utility infrastructure, which is the basis on which the project accesses the corresponding incentive regime. The incentive package available to the AI DC investor — tax, customs, land, speed and people — is set out in §17.

5.1 Why the data center anchors the master plan

  • Anchor load. Large, stable, long-duration electrical demand is what justifies building the 500/220 kV head-end substations in PK-4 and the associated cooling and connectivity infrastructure as a single coordinated programme.
  • Adjacency. PK-2 sits immediately adjacent to the head-end power infrastructure, minimising transmission distance and supporting N-2 reliability.
  • Ecosystem pull. Available compute capacity is the input that draws the research, pilot production and start-up activity planned in PK-1.
  • Reserve land is set aside within the zone for long-term data center expansion beyond the current programme.

5.2 Development typology — horizontal, modular, low-rise

Unlike a conventional industrial park, which needs comparatively little land, an AI data center campus is developed horizontally as independent low-rise modules. The report sets out four reasons this is treated as a technical and economic necessity rather than a preference:

  1. Capital efficiency. Module-by-module phasing matches capital deployment to demand and avoids a single large outlay; shared power, cooling and network infrastructure across a wide footprint reduces unit cost per MW of compute.
  2. Technology adaptability. Chips, GPUs and cooling solutions change continuously; a distributed modular layout allows upgrade, replacement or expansion of individual blocks without interrupting operating blocks.
  3. Schedule. Modules are designed, constructed and commissioned in parallel, substantially shortening delivery compared with a concentrated high-rise facility.
  4. Operations and safety. Horizontal arrangement simplifies heavy equipment installation and transport, power and fibre routing, and cooling pipework, while meeting demanding floor-loading, ventilation, heat-rejection and fire-protection requirements.

5.3 International reference projects cited in the master plan

ProjectLandBuildingsCapacity / notes
Stargate — Abilene, Texas, USA~1,100 acres (~445 ha)8Up to 1.2 GW
Frontier — adjacent to Stargate~1,200 acres10 (single-storey)—
Matrix — Sulphur Springs, Texas1,677 acres30 identical100 MW each
YTL Green Data Center Park — Kulai, Johor, Malaysia~1,640 acres (~664 ha)CampusPlanned 500 MW; Malaysia’s first hyperscale campus co-powered by on-site solar; AI infrastructure on liquid-cooled NVIDIA GB200
Thailand — Korat——~200 MW project
Thailand — Chonburi (Eastern Economic Corridor)——120–200 MW projects; national target ~1 GW by 2027

The common pattern is a large land parcel outside the urban area with low-rise modular buildings — fundamentally different from the small-footprint traditional industrial park.

5.4 Design intent for the Hue AI Data Center (AI DC — “STAR”)

Facility standard

  • Uptime Institute Tier III/IV
  • Continuous operation at 99.995% availability
  • High-performance computing (HPC) systems alongside the AI training estate

Systems

  • High-performance GPU/TPU server fleet for large-model training
  • Distributed storage architecture
  • Advanced cooling: cooling towers, CRAC/CRAH, and direct liquid cooling at rack level

06PK-3, PK-4 and PK-5

6.1 PK-3 — High-tech services and amenities (DVHH) · 88.61 ha

The central district of the park and the operational front door, with a high plot ratio reflecting concentrated mixed-use development. This is the zone counted against the statutory 15% services cap.

  • Management and operations block — Hue HTP Management Board headquarters, operating offices, a one-stop administrative centre for investors, security control and technical operations coordination.
  • Conference and exhibition centre — international conference facilities, technology exhibition and demonstration space, event and technology-fair venues (consistent with Article 25(4) of Decree 260/2026/ND-CP).
  • Commercial and financial — retail centre, commercial bank branches, financial and insurance services; legal, IP, investment brokerage and technology valuation/appraisal services (Article 25(5)).
  • Short-stay accommodation and expert services — hotel, villas, serviced apartments for experts, scientists, engineers and visiting staff, permitted inside the boundary under Article 30 as directly serving high-tech operations.
  • Social infrastructure — medical, education, sports, cultural, food and beverage, park and public service facilities for the working population.

6.2 PK-4 — Head-end technical infrastructure (HTKT) · 28.98 ha

The technical spine of the park under Article 3(5) of Decree 260/2026/ND-CP, containing:

  • Two 500/220 kV substations — large-capacity supply with N-2 redundant configuration serving the AI load
  • Water treatment plant and works — potable supply and closed-loop wastewater treatment to environmental standard
  • Logistics area — warehousing and coordination of inbound and outbound goods and materials

6.3 PK-5 — Greenery, water bodies and landscape (CX, MN) · 235.93 ha

Not a passive landscape reserve. PK-5 is designated as a living lab — a controlled field-test environment under Article 3(1) of Decree 260/2026/ND-CP, directly linked to PK-1 research activity and the International AI Robot Certification Center. Green and water areas are excluded from the 15% services cap.

  • Protective green buffer (CXCL, 19.01 ha) — safety corridor along the 500 kV overhead line and connection areas, doubling as an ecological corridor linking the zones.
  • Roads (GT, 116.08 ha) — internal and external road network connecting to the Cam Lo – La Son Expressway, the Ho Chi Minh Road and Provincial Road 15B.
  • Ben Van lake (~20 ha) — retained as a landscape feature and, per the water strategy, as a transfer reservoir.

07Power Supply and Route Redundancy Roadmap

Power is the binding constraint on this project, and it is delivered in three cumulative phases — a temporary 22 kV supply, a dual-source 220 kV supply, and a 500/220 kV supply enabled by the national power development plan amendment whose dossier is already on file (§8.2). Each phase adds a voltage level without retiring the one before it. The temporary 22 kV source is retained after the 220 kV connection is energised, and the 220 kV source is retained after the 500/220 kV substation enters operation, so that at every transition the proven source remains available while the new one is being commissioned.

7.1 Basis of record

InstrumentContent and standing
Letter No. 08/CV-HEART, 17 April 2026HEART HT statement of power supply demand for the Hue City Hi-Tech Park, Phase 1.
Hue Power Company (HPC) response letterFormal utility reply to Letter 08/CV-HEART, setting the conditions for supply at each voltage level. This is the governing instrument for §7.
Power Transmission Company 2 (PTC2) comments, 5 May 2026Transmission-side comments incorporated into the HPC response.
Working-level agreement with HPC and EVNCPC, 28 July 2026Allocation of the temporary 22 kV feeders — the agreed working basis for the short-term phase.
Establishment report (DT_BCTH_DeanKHCNHue, 12 July 2026)Sets the planning envelope: ~1,550 MW ultimate demand, of which ~1,000 MW AI data center and ~550 MW high-tech production, R&D and utilities.
Reconciliation. The establishment report states the planning envelope — what the park is sized for. The HPC correspondence states the delivery route — how and when that envelope is actually energised, and on what conditions. Where the two differ in the near term (for example, a 120 MW temporary allocation against a 150 MW Phase 1 requirement), the HPC correspondence governs and the balance arrives with the next voltage level. The 1,550 MW envelope is unchanged.

7.2 Terminology — circuit and double circuit

Vietnamese engineering usage in the correspondence follows a convention that is worth stating explicitly, because it determines how redundancy is counted:

mạch — circuit

One electrically independent circuit.

mạch kép — double circuit

Two circuits strung on the same pole line using double-circuit crossarms. This is not a bundled conductor, which is a different concept entirely.

It follows that two 22 kV double-circuit overhead lines form two physical routes but four electrically independent circuits. Circuit-level redundancy and route-level redundancy are therefore different questions, and §7.4 and §7.7 answer them separately.

7.3 Overall roadmap

Short term22 kV temporary120 MW · Q4 2026 → Q4 2027
Medium term220 kV dual sourceN-1 from Q1 2030
Long term500/220 kV+1,400 MW · PDP8 amendment required
Three-phase supply roadmap — cumulative, not sequential replacement
PhaseVoltageCapacityTimingGoverning condition
Short term22 kV (existing network)120 MWT0 Q4 2026 → T1 Q4 2027Feeder allocation agreed at working level with HPC and EVNCPC, 28 July 2026
Medium term220 kV → 110 kV → 22 kVPhase 1 balanceN-1 achievable from Q1 2030Two independent 220 kV sources required by HPC; Chan May upgrade carried on the City’s priority grid list
Long term500/220/110 kV+1,400 MWpFS dossier filed 11 Aug 2026 (§8.2)Not in PDP8 or adjusted PDP8 — planning-amendment dossier is a precondition
ULTIMATE ENVELOPE (establishment report)~1,550 MWAI data center ~1,000 MW · high-tech production, R&D and utilities ~550 MW

The retention rule is deliberate and has a direct construction consequence: the temporary 22 kV assets are not demolition scope once the 220 kV connection is live, and the 220 kV receiving station is not decommissioned when the 500/220 kV station enters service. Each becomes standing backup.

7.4 Short term — temporary 22 kV supply (120 MW)

Short-term 22 kV supply — N-1 via dual feed. Road-following 22 kV circuits from
Short-term 22 kV supply — N-1 via dual feed. Road-following 22 kV circuits from the La Son and Phu Bai 110 kV substations provide the temporary early-works supply with N-1 security ahead of the dedicated higher-voltage build-out.
La Son 110 kV substation. Source A of the short-term dual 22 kV feed
La Son 110 kV substation. Source A of the short-term dual 22 kV feed (N-1).
Phu Bai 2 110 kV substation. Source B of the short-term dual 22 kV feed
Phu Bai 2 110 kV substation. Source B of the short-term dual 22 kV feed (N-1).

The temporary phase uses the existing 22 kV network — no new transmission asset is on the critical path — and governs the Phase 1 load ramp from T0 in Q4 2026 to T1 in Q4 2027.

Temporary 22 kV feeder allocation — agreed working basis with HPC and EVNCPC, 28 July 2026
RouteSource substationFeedersCapacityCorridor
Route ALa Son 110 kV substation4 circuits
(2 double-circuit lines)
80 MWLine 1 and Line 2 share the same right-of-way and the same pole structures
Route BPhu Bai 22 circuits40 MWSeparate corridor — this is what creates route-level redundancy
TEMPORARY ALLOCATION120 MWRamp T0 Q4 2026 → T1 Q4 2027

Redundancy analysis

Within Route A
N-1

The four circuits provide N-1 redundancy at circuit level.

Common-mode exposure
4 → 0

Because Line 1 and Line 2 share the same right-of-way and pole structures, a single simultaneous event could take all four Route A circuits out at once. Circuit-level N-1 does not survive a corridor event.

Route-level cover
Route B

The separate corridor from Phu Bai 2 is therefore the actual source of route-level redundancy — not the circuit count on Route A.

Route separation — engineered out in the filed design. The shared final segment identified in the earlier concept has been resolved in the September 2026 filed configuration (§8): two independent 110 kV source substations (La Son and Phu Bai 2) feed the park over physically separate 22 kV corridors, each registered for the full Phase-1 load — true route redundancy from day one.

7.5 Medium term — dual-source 220 kV supply

Hue 220 kV substation
Hue 220 kV substation. First firm source of the medium-term dual-source 220 kV supply.
Chan May 220 kV substation
Chan May 220 kV substation. Second source of the medium-term 220 kV supply — upgrade carried on the City’s priority grid list.

HPC requires continuous supply from two independent sources taken from two different 220 kV substations. The two sources are being brought to readiness on complementary tracks — Hue 220 kV firm today, Chan May carried on the City’s priority grid list.

220 kV source readiness against the HPC dual-source requirement
SourceStatusPresent configurationPosition
Hue 220 kV substationSatisfiesOne station, two 250 MVA transformersTransformers AT3 and AT4 currently loaded at approximately 35% of rated capacity — substantial headroom available today.
Chan May 220 kV substationDoes not satisfyOne station, a single 125 MVA transformerThe power development plan to 2030 envisages an upgrade to two 250 MVA transformers. HPC has asked HEART to register its connection demand with EVN and EVNNPT. N-1 between the two sources is therefore achievable only from Q1 2030, once this upgrade is complete.

HEART receiving substation and in-park distribution

ElementConfiguration
Receiving substationSteps down from 220 kV to 110 kV via two 250 MVA main transformers
110 kV distributionDistributes at 110 kV to HTZ-SS1, HTZ-SS2 and HTZ-SS3
In-park step-downEach HTZ substation steps down further to 22 kV for distribution within the park

Internal 110 kV distribution is designed to two typical section options, selected route by route according to building density, visual amenity and safety-corridor requirements: (i) overhead line on single-pole steel towers — 25 m corridor for a single circuit, 39 m for a double circuit; (ii) underground 110 kV cable in a cable trench or cable tunnel — 25 m corridor.

7.6 Long term — 500/220 kV supply, subject to PDP8 amendment

Phase 2 adds approximately 1,400 MW, which requires connection at 500 kV.

The proposed asset

  • Hue City Hi-Tech Park 500/220 kV substation, 3 × 900 MVA
  • Connected in transit to the North–South 500 kV double-circuit line that crosses the project area
  • The corridor is already on site — four 500 kV circuits and two 220 kV circuits pass through Hung Loc

The blocking condition

HPC confirms that this substation is not included in Power Development Plan VIII, nor in the adjusted Power Development Plan VIII. HPC therefore asks HEART to prepare a dossier proposing a planning amendment for the 500/220/110 kV and 110/22 kV lines and substations supplying the project, comprising a demand statement, capacity balance and connection scheme, for submission to the competent authority for appraisal and approval. This dossier is a precondition for the entire long-term phase.

Zoning headroom. The establishment report reserves PK-4 (28.98 ha) for head-end technical infrastructure and describes two 500/220 kV substations. The HPC correspondence refers to a single 3 × 900 MVA station connected in transit. The zoning reservation is therefore not a constraint on the configuration that is ultimately approved — it provides headroom above it.

7.7 Redundancy status by phase

Redundancy by phase — N-1 transmission. Independent transmission routes feed the
Redundancy by phase — N-1 transmission. Independent transmission routes feed the park from separate upstream substations, so loss of any single source still supports the phase demand.
What redundancy actually exists at each stage — the question a delivery partner has to answer for the anchor tenant
PhaseCircuit levelRoute levelSource levelResidual exposure
Short term
22 kV, 120 MW
N-1 4 circuits on Route APartial Route B on a separate corridorTwo feeds La Son + Phu Bai 2The shared ~3 km final segment defeats both, unless separated. Phu Bai 2 carries no firm capacity or reliability commitment in the correspondence.
Medium term
220 kV
N-1 2 × 250 MVA main transformersYes two independent 220 kV corridorsNot before Q1 2030Chan May remains a single 125 MVA transformer until the upgrade lands. Until then the dual-source requirement is met on paper by Hue alone.
Long term
500/220 kV
N-2 3 × 900 MVAYes transit connection to the 500 kV double circuitYes plus retained 220 kV and 22 kV sourcesEnabled by the planning amendment now in appraisal — the pFS dossier was filed on 11 Aug 2026 and the project is carried on the City’s priority grid list (§8.2).

7.8 Technical requirements

RequirementSpecification
Supply reliabilityContinuous 24/7 supply with very high availability factor for both the high-tech production areas and the AI Data Center
Redundancy targetMinimum N+1 for data center and semiconductor loads; N-2 across the upstream source system at full build (500/220/110 kV) — supply maintained on simultaneous failure of two elements
Power qualityVoltage within ±5%; frequency within ±0.5 Hz; total harmonic distortion (THD) ≤ 5%; compliant with IEEE Std 519 and Circular 39/2015/TT-BCT
Reliability classRated-4 target consistent with the TIA-942-C connectivity specification in §10

7.9 Coordination points and critical path

These four coordination items pace the programme — and each now has a filed dossier or an agreed plan behind it (§8).

#ItemPhasePosition and required action
1Shared final segmentShort termSeparated in the filed design (§8.1) — the September 2026 registration draws on two independent 110 kV substations over physically separate corridors, converting the temporary phase to real route redundancy.
2Phu Bai 2 commitmentShort termRegistered at the full 40 MW in the filed dossier (§8.1) — Phu Bai 2 is carried as a 100% mutual-backup source, and the temporary-supply plan was agreed with Hue PC and EVNCPC on 28 Jul 2026.
3Chan May upgradeMedium termThe Chan May upgrade to two 250 MVA transformers sets the pace of 220 kV N-1; the project is carried on the City’s priority grid list (150 MVA 2026–2030), and EVNNPT engagement runs in parallel with connection registration.
4Planning-amendment dossierLong termAlready initiated well ahead of schedule — the pFS dossier for the 500/220/110 kV works was filed on 11 Aug 2026 (§8.2), keeping state appraisal off the Phase 2 critical path.
Delivery implication. Items 1 and 2 are already closed in the September 2026 filing (§8) — separated routes and dual firm sources — and items 3 and 4 have their dossiers on file. A delivery partner’s highest value is executing the connection works to the 2027 energisation date, the redundancy an anchor tenant underwrites against.

08Power Grid Connection — Filed Status · September 2026

This section records the grid-connection position as filed with the authorities as at September 2026, and supersedes the indicative short-term figures in §7 where they differ. The Phase-1 registration on file is 40 MW from two independent 110 kV sources with 100% mutual backup — the configuration required for Rated-4. Both source substations exist today, and should State and city objectives allow an earlier start, the Investor intends to accelerate the expansion roadmap on the strength of the commitment package in §20.2 (Report 25/2026).

8.1 Phase 1.1 — 22 kV connection dossier submitted

  • Dossier on file. On 28 Aug 2026 the Investor submitted Official Letter 20/CV-HEART with the full technical package (22 kV System Connection Report R5 · preliminary grid-impact assessment · real load roadmap) requesting in-principle acceptance by Hue Power Company — Step 1 of the connection-agreement sequence under Official Letters 3208/SCT-NL and 3593/HPC-KD+KH+KT. The temporary supply plan was agreed at working level with Hue PC and Central Power Corporation (EVNCPC) on 28 Jul 2026.
  • Load and reliability. Registered capacity 40 MW from the 110 kV La Son substation and the 110 kV Phu Bai 2 IP substation, each registered for the full 40 MW — 100% mutual backup, satisfying Rated-4 (highest tier, ANSI/TIA-942-C). Of the 40 MW, 37.70 MW (94.25%) is IT and cooling load.
  • Connection works. Two double-circuit 22 kV routes from La Son (~4.5 km) and one double-circuit route from Phu Bai 2 (~7 km), ACV-240 conductor; fully investor-funded (~VND 41.9 bn), completion within 2027; second transformers (63 MVA) proposed at both source substations in 2028 in step with expansion.
22kV supply line routing drawing Dz22kV-R2
Phase-1 22 kV supply routing (drawing Dz22kV-R2, attached to Official Letter 10/CV-HEART) — double-circuit routes from the 110 kV La Son and Phu Bai 2 substations.

8.2 Main supply at 110 kV and above — by phase

  • Phase-1 main scheme. Two new 110/22 kV substations — KCNC Hue 1 and KCNC Hue 2 (2 × 63 MVA each) — connecting to the 220 kV Hue substation, the 220 kV Chan May substation and the 110 kV Phu Bai 2 substation; planning supplements for the 110 kV and 220/500 kV substations proceed in a dedicated dossier alongside the City’s power development plan update.
  • PDP8 amendment — dossier submitted and under appraisal. Per MOIT appraisal criteria (Official Letter 4912/BCT-KHTC), the Investor petitioned for two in-project 500/220/110 kV substations of 2 × 900 MVA each, with ~300 m 500 kV tie-lines lying entirely inside the site boundary (Official Letter 14/2026/CV-HEART) and submitted a pre-feasibility-level dossier on 11 Aug 2026 (Official Letter 18/2026/CV-HEART, completing requirements of 2920/SCT-NL). At city level the project is on the priority grid list (1937/SCT-NL: 150 MVA in 2026–2030 · 1,400 MVA in 2031–2035). At the 16 Sep 2026 session, EVNCPC identified PDP8 inclusion of the two 500 kV substations as the key enabler for large secondary investors — and the Investor has proposed to fund the construction of both 500 kV substations itself (Report 25/2026).
Grid milestones on file (to be firmed up in the connection agreement and Feasibility Study)
MilestoneContentVoltage level
2026Construction start; ~2 MW site power22 kV temporary
2027Phase 1.1 energisation — 40 MW registered from two independent sources22 kV
2028–2030220 kV connection — ~150 MW110 kV – 220 kV
Post-2030In-project 500/220 kV substation — roadmap to GW scale500 kV

8.3 Load commitment and grid-stability package — CV 24/2026

  • Four-part assurance offered to the power sector (Official Letter 24/2026/CV-HEART, 15 Sep 2026): ① the Investor funds 100% of the grid works and hands them to the National Power Transmission Corporation (EVNNPT) on completion (Electricity Law 61/2024 Art. 5.4; Decrees 02/2024 and 77/2025); ② minimum take-or-pay payment on registered capacity of each phase, independent of actual usage — negotiating orientation 60–70% of registered capacity per current international data-center practice, with an early-termination fee of two years of minimum fees; ③ performance security by bank guarantee or letter of credit with per-phase load commitments; ④ participation in the direct power purchase mechanism (DPPA) under Decree 57/2025.
  • Two-part tariff ready. The Investor stands ready to adopt the capacity-plus-energy two-part tariff MOIT applies from 01 Jan 2026 (Politburo Resolution 70-NQ/TW) — the capacity component is precisely the registered-capacity payment mechanism offered.
  • Grid stability engineered in. A four-layer oscillation-absorption structure and a battery energy-storage system combined with supercapacitors, built in three steps 36 → 63 → 90 MW per the filed pFS and oriented to ~200 MW at full scale — configured as a zone-common grid-stability facility covering a portion of in-park capacity (optimal storage share 20–40% of load, the capital-efficient hybrid point) rather than full self-supply, with the supply plan developed under the exclusive co-development track, third-party supply included; a milestone-verified load-ramp MOU is proposed with Hue Power Company and EVNCPC, witnessed by the Department of Industry and Trade — each load step starts only after the previous step passes grid-impact verification.
Why this matters to a delivery partner. The take-or-pay commitment, self-funded grid works and staged BESS give the power sector bankable certainty — which is exactly what unlocks early substation build-out and the accelerated expansion the Investor intends to pursue.

8.4 Medium-to-long-term generation sources

  • National policy tailwind. MOIT Report 760/BC-BCT to the Prime Minister orients the amended PDP8 toward fast-deploying generation and strengthened cross-border interconnection and imports — precisely the source configuration the park has petitioned for.
  • Investor petition. Once the supply scheme is updated into the amended PDP8, prioritise imported Lao hydropower over the central-region 220/500 kV interconnection trunks as the park’s medium-to-long-term source: competitive price, low emissions, feasible schedule.
  • Chan May – Lang Co LNG power plant. The Investor has confirmed it will study a long-term co-investment structure, inviting a major Korean LNG-power group to hold the majority role for co-development serving the park and data center directly. Preconditions: gas-price/tariff mechanism, PPA, and fit with the amended PDP8 schedule. Findings will be reported to the People’s Committee.
Laos–Vietnam central region grid interconnection diagram
Lao–Vietnam power-import interconnection, central region (source: PECC2 — Lao-side 500 kV trunk option, amended PDP8) — basis for the medium-to-long-term imported-hydropower petition.
Sources. Official Letters 10/CV-HEART, 20/CV-HEART, 14/2026/CV-HEART, 18/2026/CV-HEART; MOIT Report 760/BC-BCT; Department of Industry and Trade letters 3208, 2920, 1937/SCT-NL; September 2026 Report to the People’s Committee.

8.5 A-to-Z power architecture — from renewable DPPA to in-park distribution and grid stability

What a hyperscaler actually diligences is not a headline DPPA tariff but the reliability of the whole chain, from generation to delivery. HEART therefore structures the complete A-to-Z package in advance: wide-area renewable procurement over the national grid and on-site generation in parallel, self-funded grid works handed to EVNNPT, a 100% underground in-park distribution network held by the zone’s own retail business unit, and a staged storage-based stability stack — elevating the site from “powered land” to “a site with a complete, executable power solution”. For the Phase-1.1 40 MW package, an exclusive co-development track with a Renewables Major candidate is in structuring under NDA — DPPA registration and settlement expertise, wide-area renewable aggregation, a supply plan for the zone-common BESS stability facility (third-party supply included) and delivery guarantees with renewable-attribute transfer — against anchor demand visibility of up to ~15 years, while the zone electricity-retail right itself remains with HEART.

The park’s supply position, in plain terms: at 22 kV, two circuits of 40 MW each are allocated (AIP) and building now, with a further 40 MW expandable on the same corridors; at 110 kV, two circuits of 150 MW each are secured — one available immediately, the other built out against a demand-backed commitment; and at 500 kV, the in-park substations are moving through the PDP-8 amendment, with the newly planned nearby 500 kV substation being moved inside the park on a demand basis — the platform for a Giga-Scale Campus. The three levels are cumulative, not substitutional.

The Park’s Supply Ladder — secured today, expandable on demand 22 kV SECURED — AIP ALLOCATION 2 circuits × 40 MW each from two existing 110 kV substations +40 MW expandable on the same corridors NOW · energisation 2027 110 kV SECURED — DUAL CIRCUITS 2 circuits × 150 MW each circuit 1 available immediately circuit 2 built out against demand-backed commitment (take-or-pay) IMMEDIATE + COMMITTED EXPANSION 500 kV PDP-8 AMENDMENT IN PROGRESS In-park 500/220/110 kV substations — 2 × (2 × 900 MVA) newly planned nearby 500 kV substation moved inside the park — demand-based siting ~300 m tie-lines entirely in-boundary · cumulative with the levels below GIGA-SCALE CAMPUS · 1,000 MW class ≈ 3,600 MVA transformation on site whole-zone envelope registered: 1,550 MVA Cumulative, not substitutional — each voltage level adds capacity without retiring the one below One-line summary: two 22 kV circuits are allocated and building now; two 110 kV circuits of 150 MW stand behind them; the 500 kV campus stage is moving through PDP-8.
The supply ladder — 22 kV (2 × 40 MW, AIP-allocated, +40 MW expandable) → 110 kV (2 × 150 MW; one immediate, one demand-committed) → 500 kV in-park substations in the PDP-8 amendment toward the Giga-Scale Campus.
HEART Power System — A to Z Single-Line Architecture Renewable DPPA procurement → national grid & in-project substations → in-park 22 kV duct distribution → grid-stability stack A · GENERATION & PROCUREMENT B · NATIONAL GRID & IN-PROJECT SUBSTATIONS C · IN-PARK DISTRIBUTION, LOADS & STABILITY Off-site utility-scale RE (wide-area) step-up vDPPA · CfD settlement — RE attributes transferred (ND 57/2025 → 243/2026) On-site PV (plots & rooftops) + BESS on-site BESS surplus sales ceiling 50% (Art. 6.3) 500 kV national grid SS-1 · 500/220/110 kV 2 × 900 MVA SS-2 · 500/220/110 kV 2 × 900 MVA ~300 m tie-lines, entirely in-boundary 220 kV — Hue · Chan May sources 110 kV level: 2 circuits × 150 MW — one immediate, one against demand-backed commitment La Son 110 kV EXISTING Phu Bai 2 110 kV EXISTING 22 kV circuit A — 40 MW AIP · 2 CIRCUITS 22 kV circuit B — 40 MW · 100% mutual backup (N-1) EVNNPT HANDOVER — grid works self-funded by the Investor, transferred on completion (Electricity Law 61/2024 Art. 5.4) ZONE ELECTRICITY RETAILER BU — held by the PPP entity (Arts. 8a & 2.1c, ND 243/2026 · the HTP as a DPPA zone, Art. 3.21) Zone intake substation 22 kV switchgear 100% UNDERGROUND DUCT-BANK RING — dual physically separate routes RMU loop AI DC HALLS 40 → 150 MW → 1,000 MW class HIGH-TECH PLANTS R&D · utilities ~550 MW on-site RE feed GRID-STABILITY STACK zone-COMMON shared facility · four-layer absorption L1–L2 · supercapacitors (ms–s) L3 · PCS-BESS — staged 36 → 63 → 90 MW (pFS) covers a share of park load (opt. 20–40%) · to ~200 MW L4 · long-duration shifting milestone-verified load-ramp MOU BANKABLE OFFTAKE FRAME Take-or-pay on registered capacity orientation 60–70%, usage-independent Two-part tariff ready capacity + energy, from 01 Jan 2026 (NQ 70-NQ/TW) Bank guarantee / LC per-phase load commitments Retail & settlement margin 7-day DPPA connection counterparty (zone gate) LEGEND transformer circuit breaker busbar PV array wind BESS energy flow DPPA contract / settlement EVNNPT handover boundary zone retailer BU boundary Symbols follow IEC 60617 single-line conventions · configuration per filed dossiers (Sep 2026), figures fixed in the FS
A-to-Z single-line architecture — generation and DPPA procurement, national-grid and in-project substations (EVNNPT handover boundary marked), and the in-park 22 kV duct-bank ring with the grid-stability stack, drawn in IEC 60617 single-line convention. Configuration per the September 2026 filed dossiers; figures fixed in the FS.
Legal frame — the decrees that make this executable

DPPA under Decree 57/2025, as amended by Decree 243/2026 (in force 26 Jun 2026, no transitional period): data centers written in as qualifying large consumers (Arts. 3.23, 2.1b); the high-tech park as a DPPA zone (Art. 3.21); a zone electricity-retailer regime (Arts. 8a, 2.1c); the dedicated-line price ceiling removed (Art. 6.1.b); rooftop-surplus sales raised 20% → 50% (Art. 6.3). Two-part tariff applies from 01 Jan 2026 (Resolution 70-NQ/TW); grid-works handover rests on Electricity Law 61/2024 Art. 5.4.

Differentiators — a supplier that is also the offtaker

The AI data center’s own committed load anchors the zone (94.25% of the Phase-1.1 registration), so demand risk is structurally internalised — no stranded-intermediary exposure. As zone retailer, HEART is the counterparty that must connect a tenant’s DPPA within seven days — the gatekeeping position in the zone’s electricity market. Physical base: two existing 110 kV sources at 100% mutual backup, and a 100% underground duct-bank network on two physically separate routes.

Economic value — procurement and monetisation

Hybrid procurement (grid + on-site solar-BESS + off-site vDPPA) targets a blended cost of USD 42.9–49.0/MWh against the first commercial DPPA CfD benchmark of 61.0 — up to USD 12–18/MWh of structural advantage — with 24/7 carbon-free matching of 57–69% offered as a premium feature to anchors. The 50% surplus ceiling multiplies monetisation headroom 2.5×, and the take-or-pay plus two-part-tariff frame turns the load into bankable revenue that unlocks early substation build-out.

Infrastructure superiority — why this park leads the region

Two in-project 500/220/110 kV substations of 2 × 900 MVA each with ~300 m in-boundary tie-lines; a four-layer oscillation-absorption stack with BESS staged 36 → 63 → 90 MW toward ~200 MW; integrated power-and-water SCADA. Against a region where Viet Nam operates ~73 MW of data-center capacity and new 100 MW connections take 2–3 years, and Thailand can serve 18.7% of applications, HEART’s filed track runs to 2027 energisation — time-to-power is the product.

09Cooling Water Infrastructure

The dominant loads — large-scale AI data centers and high-tech manufacturing (semiconductor, robotics, electronics) — are all in the very high cooling-water demand category with demanding purity requirements. Supply is structured as a multi-source strategy with redundancy.

Cooling-water transmission — DN1200 main. Raw water is drawn at the Ta Trach res
Cooling-water transmission — DN1200 main. Raw water is drawn at the Ta Trach reservoir (main and backup intakes + pump station) and conveyed via the DN1200 transmission main to the main valve station, then distributed through the multi-branch valve network across the park.

9.1 Demand profile

Cooling water demand — phased with operating capacity
PhaseOperationPower (MW)Load typesRaw water (m³/day)
Phase 1Q4 2027150AI DC; high-tech production; R&D; utility infrastructure~13,000
Phase 2to 20311,550Large-scale AI DC; semiconductor; robotics; high-tech production~100,000

Actual capacity ramps with tenant and secondary-investor demand; the maximum for each phase is not necessarily reached immediately.

9.2 Primary source — Ta Trach reservoir

Ta Trach reservoir
Ta Trach reservoir. Primary raw-water source feeding the park cooling system via the DN1200 main.
Ta Trach reservoir
Ta Trach reservoir. Large live storage underpins year-round cooling-water supply security.
Ta Trach dam — main dam and flood-season spillway discharge
The Ta Trach dam — a national-grade structure, not a mere reservoir. (left) The main dam and reservoir; (right) flood-season discharge through the spillway beside the hydropower plant — the flood-control mission in operation (photographs: Ta Trach reservoir project records, HEC II).
State-managed, top-tier dam — the facts on record (Report HEART-A-QHPK-RPT-001-EN-Rev02, Section VI). In operation since 2016 as a first-class civil work: 717 km² basin, 646 million m³ total storage, main dam ~1.1 km long — the largest earth dam in Southeast Asia at its completion — with a ~21 MW hydropower plant below the dam (generating since 2014). One of Viet Nam’s four especially important dams (Prime Minister’s Decision 124/QĐ-TTg, 2019) and a work of importance to national security (Decision 166/QĐ-TTg, 2017), operated under the Prime Minister-issued inter-reservoir procedure for the Huong basin (Decision 1606/QĐ-TTg — 14 reservoirs coordinated, structure safety verified to the 1/1,000-year check flood). In the historic 2020 flood its regulation kept the city of Hue about 1.1–1.2 m shallower — the Park lies in this protected lower basin, so the State’s dam upstream and the Park’s own 1/1,000-year canal system work on the same event. 25-year cooling-water security therefore rests on a State-operated, top-tier structure with an institutional operator under the Ministry of Agriculture and Environment — not on a local pond.
Plan of the cooling-water supply from the Ta Trach lake — drawing HHTP-P1-RWS-003
Plan of the cooling-water supply from the Ta Trach lake (drawing HHTP-P1-RWS-003, conceptual design, 9/2026) — the outside-zone transmission line from the lake to the planning boundary, the Segment 2 canal, and the in-zone distribution to the cooling-water canals between the plots.
Confirmed by the reservoir operator — 16 Sep 2026. At the Chairman’s working session, the Ta Trach operating company confirmed that even the reservoir’s minimum regulated flow of ~150,000 m³/day comfortably secures the project’s full 100,000 m³/day requirement. The Investor purchases raw water at the reservoir and builds all in-fence works itself (Report 25/2026).
  • Storage: 420 × 10⁶ m³ at normal water level. Managed by Irrigation Investment and Construction Management Board No. 5, Ministry of Agriculture and Environment.
  • Existing licence: Surface water exploitation licence No. 275/GP-BTNMT dated 28 Oct 2022, permitting 2.0 m³/s (~172,800 m³/day) for domestic and industrial supply.
  • Project-specific confirmation: By Official Letter No. 2744/SNNMT-TN dated 20 Apr 2026, the Hue City Department of Agriculture and Environment formally confirmed that HEART HT’s abstraction requirement of 100,000 m³/day (1.157 m³/s) is fully compatible with the Ta Trach source, via auxiliary dam No. 4.
  • Preliminary intake concept: pump station on the bank of the Ta Trach River downstream of the hydropower dam — no structural impact on the dam — combined with Ben Van lake (Hung Loc Commune) as a transfer/storage reservoir.
  • Proximity: approximately 2 km from the park boundary.

9.3 Backup source — Truoi reservoir

To raise reliability in adverse scenarios — extended dry season, pipeline failure, maintenance outage — Truoi reservoir (Phu Loc area, useful storage approximately 60 × 10⁶ m³) is under study as a supplementary and standby source. Truoi sits on a catchment independent of the Huong River, diversifying supply and removing single-asset dependency.

Allocation status. The Phase 2 requirement of 100,000 m³/day is matched exactly by the written confirmation obtained from the Hue City Department of Agriculture and Environment, and sits within the 172,800 m³/day already licensed at source. The Truoi reservoir is therefore carried as redundancy and dry-season resilience rather than as a volume gap to be closed. See §20.

10Fiber and Connectivity

Connectivity is specified to TIA-942-C Rated-4, structured around four core requirements. Phase 1 operates at 150 MW from Q4 2027; Phase 2 (2029–2031) scales to approximately 1 GW.

Fiber & cable network — regional reach. The park sits within diverse-route r
Fiber & cable network — regional reach. The park sits within diverse-route reach of the regional backbone and coastal cable landings, supporting the carrier-diverse, physically-separated paths required for TIA-942-C Rated-4 connectivity.
TIA-942-C Rated-4 requirements versus existing infrastructure
#RequirementStatus and solution
1Minimum two independent submarine cable systems from two separate landing stations — 10–20 Tbps for Phase 1, 100+ Tbps for Phase 2Available Two independent systems already land in Central Vietnam: APG at Da Nang (RTD 23 ms) and SJC2 at Quy Nhon (RTD 21 ms)
2Two domestic routes to the landing stations on physically separate corridorsAvailable Both VNPT and Viettel operate independent routes (aerial and buried); the solution is to run the two carriers’ routes in parallel
3A terrestrial multi-country route, Vietnam – SingaporeAvailable VNPT operates VSTN Da Nang – Singapore at 2 Tbps, expandable to 12 Tbps
4Carrier-neutral Meet-Me Room with ROADM for a minimum of three operators, operational at least three months before COD Q4 2027To build Both carriers have confirmed readiness to connect into the carrier-neutral room inside the park

VNPT and Viettel have both formally confirmed readiness to provide fibre connectivity as soon as investor demand is established — including site survey, detailed technical design, priority resource allocation and alignment with the project’s overall programme.

11Telecommunications Network — Implementation Plan

Two national carriers have confirmed in writing that they can meet the project’s connectivity requirements — Viettel (Letter 705/HUE-GPCNTT) and VNPT (Letter 1028/VNPTHUE-KTDT) — each committing to field survey and detailed design. In practice, fiber build-out typically runs ahead of power-line corridor schedules.

11.1 International connectivity — two landing stations, heterogeneous routes

  • Primary gateway — Da Nang (~85 km). APG submarine cable (23 ms RTD to Singapore) · VSTN terrestrial route (39 ms — failure-mode independent of submarine systems) · ALC submarine cable (landing expected 2026).
  • Second gateway — Quy Nhon. SJC2 (21 ms) · ADC.
  • Capacity. Carrier-available capacity in 2027: 4.0–8.0 Tbps. Targets: Phase 1 — 10–20 Tbps; Phase 2 — above 100 Tbps. Planning density 70–130 Gbps/MW.
International connectivity schematic — two landing stations
International connectivity schematic — two landing stations (Da Nang · Quy Nhon), heterogeneous submarine and terrestrial routes, two carriers.

11.2 Park–landing-station route — procurement approach

  • Two parallel tracks under negotiation with the carriers: (i) leased infrastructure — two underground dark-fiber routes direct to the Da Nang landing station, taken per wavelength or as long-term IRU; or (ii) direct investment / co-investment in the underground route with the carrier. Selection on commercial terms at negotiation, on the principles of maximum undergrounding and two physically independent routes.
  • Schedule coupled to power. International capacity registration activates on approval of the power-supply scheme (submarine capacity activation ~8–10 months; domestic transmission expansion ~12 months); first registration targeted Q4 2026 – Q1 2027.
External telecom connection plan on satellite imagery
External telecom connection plan — carrier trunk routes and landing-station links on satellite imagery (10 Sep 2026).

11.3 In-park redundancy and duct infrastructure — 100% underground

  • Redundancy configuration. Two physically independent park entries (A/B, ≥20 m apart, different roads and structures); two carrier-neutral Meet-Me Rooms (minimum three carriers); ring-structured in-park backbone — a single cut still routes the reverse direction of the ring.
  • Duct infrastructure. HDPE Ø110 duct banks — 4–6 ducts on trunk sections, 12–16 ducts (plus spares) on data-center approaches, 1–2 air-blown-fiber ducts initially; manholes ≥2.0 × 1.5 m at 50–80 m spacing; later expansion no-dig; dedicated trench, segregated from the 22 kV underground power corridor (QCVN 07-3 · 07-5). All outside-plant network in the park runs underground — applying precedent already approved at domestic technology parks.
100% undergrounding configuration — dual entries, carrier-neutral MMR, ring backbone
100% undergrounding configuration — two independent entries, carrier-neutral Meet-Me Rooms, ring trunk backbone.
Sources. Viettel Letter 705/HUE-GPCNTT; VNPT Letter 1028/VNPTHUE-KTDT; telecom implementation study attached to the September 2026 Report to the People’s Committee.

12Expressway Access & Internal Road Network

The park is one of very few Vietnamese high-tech sites with direct expressway frontage: the CT01 (Cam Lo – La Son) expressway forms the north and east boundary, and every metre of access road and the future interchange lies inside the project boundary — no third-party land to assemble, single-owner delivery.

12.1 Access secured today — permanent solution in engineering

  • Phase-1 access is in service now. The existing overpass on CT01 serves Phase-1 traffic; the load-capacity survey terms of reference have been issued and a temporary strengthening plan prepared, so construction logistics can begin in 2026 — per Report 25/2026, Phase 1.1 deliberately proceeds on the existing overpass to keep the programme at full speed, with the permanent interchange delivered in parallel with or immediately after Phase 1.1, and no tolls charged on the connection.
  • Being engineered for GW-scale logistics. The permanent solution — a four-lane grade-separated interchange with an approach bridge of ~200 m, structurally rated for super-heavy haulage of 200 tonnes and above (220/500 kV transformers and large plant) — is in engineering now, on the basis of the external-connection study completed 31 Aug 2026.
  • All within the boundary. The connecting roads and the interchange sit inside the project boundary, so land, design and construction are delivered under one hand.
Existing overpass on CT01 — Phase-1 access in service
Phase-1 access in service today — the existing overpass on CT01 at the project area: (a) position on the corridor, (b) satellite close-up. Survey and strengthening plan prepared; the permanent interchange, now in engineering, takes over from Phase 2.
Roads and interchange within the project boundary
Single-owner delivery — the access roads and the planned interchange lie entirely within the project boundary (technical consultant material, September 2026).

12.2 Delivery path — mapped, funded and precedent-backed

  • Approval route mapped, correspondence ready. Expressway connection approval runs Ministry of Construction → Directorate for Roads of Vietnam → Road Management Unit II (Decree 241/2026/ND-CP; connection agreement per Art. 27, Decree 165/2024/ND-CP). The full technical study is complete and the registration correspondence pack is ready to file.
  • Fast-track channel identified. The CT01 La Son – Hoa Lien section toward Da Nang is being widened to four lanes right now — attaching the interchange works to that live programme is the identified fast-track, with City-level coordination.
  • Investor-funded, ready to execute. HEART stands ready to build the interchange directly, with funding available immediately on assignment, under the customary cost-offset practice (deduction against land rent, taxes and fees). This is the proven Vietnamese model: at the Hau Giang biomass power plant and at the Vinh Tan power centre / Pacific general port, investor-delivered connector roads and junctions achieved schedule certainty and were handed to the authorities on completion.
Corridor photo record · CT01 La Son – Hoa Lien
La Son – Hoa Lien expressway corridor photo 1
La Son – Hoa Lien expressway corridor photo 2
Corridor photo record · four-lane widening in progress
La Son – Hoa Lien expressway corridor photo 3
La Son – Hoa Lien expressway corridor photo 4

12.3 Preparation status and internal road network

External connection — preparation status (September 2026)
StepContentStatus
① Technical studyExternal-connection study package (31 Aug 2026): interchange typology, super-heavy design criteria, reference procedure / time / costComplete
② Central correspondenceConnection registration pack via MOC → DRVN → RMU IIReady to file
③ Widening-programme attachmentAttach the interchange to the live La Son – Hoa Lien four-lane widening — City coordinationCoordination scheduled
④ Connection agreementWith the road authority — interchange position and design prepared for agreementPrepared
⑤ Haul-route surveyBridge load capacity, clearances, temporary strengthening (ToR issued); super-heavy permit procedure draftedToR issued · permits drafted
Internal road network — fully investor-funded. ~60 km in total — 30 km of four-lane and 30 km of two-lane roads on 116.08 ha of traffic land, 100% investor-funded within Pillar A, engineered together with the flood-relief canal network (§13.2).
Sources. External-connection study (31 Aug 2026); Decree 241/2026/ND-CP; Decree 165/2024/ND-CP Art. 27; phasing drawing HHTP-P1-GL-001; September 2026 Report to the People’s Committee.

13Site and Ground Conditions

13.1 Topography

Of the 1,081 ha, approximately 700–800 ha is topographically straightforward to develop; the remainder is upland and natural water body retained for landscape value. Approximately 79.5% of the site lies in the 5–30 m elevation band on competent granite bedrock, giving a bearing safety factor of 15–50× data center requirements — the condition that underpins siting PK-2 heavy loads here.

Elevation distribution across the project area
Elevation bandShare of survey pointsCumulativeTerrain characterBuildability
0 – 5 m0.4%0.4%Low-lying — landscape and water use, excluded from platformsBudgeted earthworks where developed
5 – 10 m11.7%12.1%Low ground along streamsRequires ground improvement
10 – 15 m19.1%31.2%Gentle slopeBuildable
15 – 20 m23.2%54.4%Priority development areaOptimal
20 – 25 m25.1%79.5%Priority development areaOptimal
25 – 30 m13.2%92.7%Low hills, moderate reliefBuildable
30 – 50 m4.9%97.6%Moderate hillsConstrained
50 – 65 m+2.4%100%High hills, green beltNot built on

13.2 Geotechnical, hydrology and climate

Geology

Paleozoic and Mesozoic intrusive complexes with Cenozoic fluvial, fluvio-marine and marine sedimentary units — limestone, clay, sandy clay, sand, kaolin and gravelly sandy clay. No geological faults cross the planning area. Ground conditions are generally suitable for high-rise construction.

Climate

Tropical humid monsoon. Two seasons: dry from March to August, wet from September to February. Mean temperature 25 °C; annual rainfall 2,800–3,400 mm.

Hydrology

Dense network of rivers and channels. The Song Nong rises in the low hills and runs through the centre of the commune, with major tributaries (Khe Ngang, Khe Chua, Khe Trai, Khe Bong, Khe Son). Ben Van lake contributes approximately 20 ha of surface water.

Corrosion environment

Distance to the coast exceeds 20 km — above the ASHRAE A2 salt-corrosion threshold. Electronics sited more than 15 km from the sea do not require special corrosion protection, reducing equipment maintenance cost by an estimated 15–20% over a 20-year life relative to a coastal location.

Flood design basis — 1-in-1,000-year, zero inundation. ★ The Phase-1.1 flood-relief channel system is designed against an extreme flood of 1/1,000-year return period (HHFP-P1-RWS-003) — an order of magnitude beyond the 1/100-year basis common for Vietnamese industrial estates. Combined with the site’s elevation profile (79.5% at 5–30 m; only 0.4% below 5 m, excluded from platform use), this underwrites the project’s absolute zero-inundation performance guarantee for the data center and technical platforms — carried as a core technical condition in §18.4 and binding on the delivery scope in §21.
Basis of the zero-inundation guarantee — four engineered layers
LayerEngineering basis
① Flood-relief canal networkPerimeter and internal flood canals sized to the 1/1,000-year extreme flood (HHFP-P1-RWS-003) intercept upstream catchments and route extreme flows around — never across — the development platforms.
② Controlled cooling-water flow routingProcess and cooling water enters and leaves the platforms only through engineered, valved conveyance routes (twin independent Ta Trach · Truoi raw-water lines and dedicated return channels) — no uncontrolled watercourse touches a data hall platform.
③ Upstream Ta Trach dam — hydropower-dam classThe Ta Trach dam (646 million m³, first-class civil work, largest earth dam in Southeast Asia at completion) is one of Viet Nam’s four especially important dams (PM Decision 124/QĐ-TTg) and a work of importance to national security (Decision 166/QĐ-TTg), its structure verified to the 1/1,000-year check flood under the PM-issued Huong-basin operating procedure (1606/QĐ-TTg) — active upstream regulation that attenuates extreme events before they reach the park catchment (in 2020 it kept Hue ~1.1–1.2 m shallower).
④ Professional dam operationThe reservoir is operated by Ta Trach Irrigation Works Exploitation Co., Ltd — the operating manager under the Ministry of Agriculture and Environment (converted from Irrigation Board 5 on 01/7/2026) — a single-purpose professional dam operator with which the Investor cooperates on intake works and agreed dry-season/flood-season operating priorities (Document 58/CV).
Phase 1.1 flood-relief channel plan — 1/1,000-year design basis
Flood-relief channel planning, Phase 1.1 — 1/1,000-year extreme-flood design basis (HHFP-P1-RWS-003, concept design). The channel network intercepts upstream catchments and routes extreme flows around the development platforms, securing the zero-inundation condition.

13.3 Existing land use and population

  • Hung Loc Commune was formed on 1 July 2025 by merging Loc Son town and Loc Bon and Xuan Loc communes. Population approximately 32,586 across 95.62 km² — density approximately 341 persons/km², low to moderate. 17 hamlets and one village.
  • Employment: of 32,586 workers, approximately 80% are in non-agricultural sectors and 20% in agriculture, forestry and fisheries.
  • Existing cover: production forest plantation with the Ben Van resettlement lake (~20 ha) — suited to an ecological landscape strategy.
  • Resettlement: per the 1:10,000 cadastral review (Loc Bon, 2026), approximately 180 households concentrated in Ben Van, Duong Loc and Hoa Loc hamlets. No mass relocation is required, and site formation cost is marginal relative to comparable parks — the report contrasts this explicitly with the land acquisition difficulties experienced at Hoa Lac HTP. Local residents are targeted for retraining and occupational transition into the park.

14Development Roadmap and Business Plan

14.1 Positioning

The park is proposed as a multi-sector, open-format high-tech park with the AI data center as core infrastructure — not as an ancillary item. The report states plainly that this model has no precedent in Vietnam. It is positioned as a national-grade high-tech park under the Hue City People’s Committee, with one-stop licensing within 90 days.

14.2 Strategic roadmap

Development roadmap — Hue High-Tech Park
StagePeriodFocusCommitted milestones
G1 — Foundation2025–2027Sign 1–2 anchor tenants for hyperscale infrastructure leasing (100 MW+); establish the one-stop legal mechanismAnchor investor MOU signed; Phase 1 land handover of approximately 100–200 ha
G2 — Expansion2028–2031Robotics R&D district; on-demand compute leasing for enterprises and Hue University; attract 3–5 further data center and robotics investors300 MW of data center in operation; 10+ robotics companies; 2,000+ high-skill technical jobs
G3 — Full build2032+Fully integrated AI data center + robotics + biotech park; national data center; AI–robotics start-up ecosystem500 MW+ of data center; top-3 in ASEAN for large-scale AI infrastructure leasing

14.3 Implementation phasing

2026

Approvals

Complete the procedures for submission to the Ministry of Science and Technology and the Prime Minister for approval of the establishment scheme.

2026 – 2027

Master plan and Step 1 land (200 ha)

  • Master plan for the park at Hung Loc Commune; boundary marker installation; master plan approval
  • Step 1 area: 200 ha, to be confirmed at the land-use-right allocation stage under the Land Law. Effective delivery of Step 1 conditions approval of subsequent steps.
  • Infrastructure design and construction to the fence line: the main access road from the La Son – Tuy Loan Expressway to the park gate, power lines and water mains
  • Management Board operations building
  • Landscape planting programme and ornamental plant propagation
2026 – 2030

Human capital and national laboratories

  • Priority delivery of the high-tech workforce development project
  • Joint training programmes in IT and biotechnology — capable of supplying high-tech personnel from 2028
  • Establish two national key laboratories in IT and biotechnology
  • Build up software and IT enterprises, biotechnology firms using indigenous raw materials, and high-tech pharmaceutical producers
  • International investment promotion targeting foreign high-tech enterprises
2030 – 2035

Step 2 — expansion to 500 ha

  • Step 2 area increases from 200 ha to 500 ha
  • Complete platform works across the functional zones
  • Scale up the infrastructure company’s capacity to meet investor demand
  • Admit only enterprises producing high-tech products

14.4 Priority sectors

To 2030

Information technology (including the AI data center), biotechnology, and high-tech applications in medicine and pharmaceuticals.

Post-2030

Adds semiconductors, AI, IoT, electronics and informatics, energy, new materials, pharmaceuticals, computer and office equipment, communications equipment and scientific instruments. Robotics and automation runs across both horizons as a designated national strategic technology.

Workforce target: 10,000 digital-sector personnel engaged in high-tech and strategic-technology production and business in the park by 2030.

15Phased Implementation Plan — 40/30/30 · September 2026

This section consolidates the phased implementation plan reported to the Chairman of the Hue City People’s Committee in September 2026 (Report “Kế hoạch thực hiện phân kỳ Khu công nghệ cao thành phố Huế”). Area and budget figures are provisional allocations at a 40/30/30 ratio; definitive figures will be fixed in the 1/2,000 zoning plan and the Feasibility Study.

15.1 Why Hue — five siting conditions, met simultaneously

Hyperscale AI data centers are not sited on land rent; they are sited on five conditions that must all be in place at the moment of the investment decision. Several Vietnamese provinces moved earlier on policy, yet none operates a hyperscale AI data center — because the five conditions were never met at once. Hue meets all five:

1 · Power to GW scale
2 × 110 kV

Phase 1: 40 MW from two independent 110 kV substations (La Son and Phu Bai 2 IP), each registered for the full 40 MW — 100% mutual backup, meeting Rated-4 (ANSI/TIA-942-C). Phase 2: ~150 MW via 220 kV. Post-2030: in-project 500/220 kV substation. The 500 kV / 220 kV transmission corridor crosses the area — no new line corridor required.

2 · Cooling water
100,000 m³/day

Within the existing 2.0 m³/s licence of the Ta Trach reservoir (useful storage 409.65 million m³); two independent routes (Ta Trach · Truoi); hybrid evaporative-plus-recirculation design for the dry season.

3 · International routes
2 landing stations

Da Nang (~85 km) and Quy Nhon; heterogeneous submarine and terrestrial routes; two carriers have confirmed capability in writing, with 4–8 Tbps available in 2027.

4 · Contiguous land
1,081 ha

A single contiguous parcel, 955.53 ha of production forest, low resettlement count — wide enough for modular data center build-out to GW scale on one site.

5 · Supporting conditions
~18 km

Distance from the coast limits salt corrosion of cooling plant and servers; direct access to the CT01 expressway and to Phu Bai and Da Nang international airports.

Target customers
40 MW+

Global big tech, US-export-approved neo-cloud providers and top-tier global data center operators — the only groups able to bring latest-generation AI chips into Vietnam. Their entry threshold is 40 MW+ with a GW expansion path on a single site at Rated-4/2N; small, non-expandable plots do not qualify.

15.2 Phasing structure — three phases, Phase 1 split 1.1 / 1.2

  • Layout. The 1,081 ha area divides into four sectors: Phase 1.1 in the north-east, adjoining the main transport axis (started first); Phase 1.2 at the centre; Phase 2 in the south adjoining La Son IP; Phase 3 in the remaining west.
  • Division criteria. ① spread the compensation and site-handover workload; ② sequence access to external utility tie-in points (power – water – telecom – roads); ③ bring initial demand (AI data center, technology zone) into operation early.
Phasing plan drawing HHTP-P1-GL-001
Phase division plan. Concept-design phasing drawing HHTP-P1-GL-001 (September 2026): Phase 1.1 north-east · Phase 1.2 centre · Phase 2 south · Phase 3 west.
Provisional area and budget by phase (40/30/30 allocation of USD 315.3 m committed trunk-infrastructure investment)
PhasePeriodProvisional areaProvisional budgetFunding source
1.12026~262 ha (24%)USD 50.0 m2026 own equity — incl. USD 30.04 m compensation, support and resettlement cost borne entirely by the Investor (no land-rent offset requested)
1.22027~170 ha (16%)USD 76.1 mAfter financial close, combined with debt
Σ 12026–2027~432 ha (40%)USD 126.1 m2026 equity + 2027 debt
22028–2030~324 ha (30%)USD 94.6 mAfter financial close, combined with debt
32031–2032~324 ha (30%)USD 94.6 mSubject to phase-transition criteria
Total2026–20321,081 ha (100%)USD 315.3 mCommitted total per Official Letter 17/2026/CV-HEART
Phase-transition criterion. 60% industrial-land occupancy of the preceding phase, or completion of that phase’s technical infrastructure (voluntarily referencing Article 8.4 of Decree 35/2022/ND-CP).
Phase 1.1 layout
Phase 1.1 layout (HHTP-P1-GL-001, September 2026, concept design). North-east sector adjoining the main transport axis; the southern parcel cluster reserves the Phase-1 AI data center site. Compensation, grading and initial power supply proceed within 2026.
Flood relief channel plan Phase 1.1
Flood-relief channel planning, Phase 1.1 (HHFP-P1-RWS-003, concept design) — extreme-flood protection designed to a 1/1,000-year return period.
Repeated for emphasis — the park does not flood. The 1/1,000-year design basis above is roughly ten times more severe than the 1/100-year basis used by typical industrial parks, and the resulting absolute zero-inundation guarantee is one of the project’s core technical conditions (§18.4). It is delivered by four engineered layers working together: the flood-relief canal network, fully controlled cooling-water flow routing, the upstream Ta Trach dam built to hydropower-dam design standards — a fundamentally higher class than ordinary reservoirs — and professional operation by the dedicated state-owned Ta Trach dam operator (§13.2). For hyperscale operators screening central-Vietnam sites after recent regional flood events, this is a deliberate, documented differentiator.

15.3 Two-pillar structure and investor commitment

  • Pillar A — trunk infrastructure (PPP–BOT). USD 315.3 m, 100% private capital, no state capital and no government guarantee; 25-year operation, contract end 01 Jan 2052; equity ≥ 30% / debt ≤ 70%; financial close within 12 months of contract signing; performance security 1–3% accepted.
  • Pillar B — AI data center (separate project under the Investment Law). Phase-2 scale USD 2,330 m (above the VND 30,000 bn special-incentive threshold, Art. 20 Investment Law); debt : equity 70 : 30; sustainability targets — PUE 1.28 and 100% renewable energy by 2030. Financial reference indicators are disclosed to NDA + KYC counterparties only, through the secured data room (§16).
  • Single counterparty, clean structure. The PPP project enterprise is established and 100%-owned by HEART HT; the Investor and the project enterprise together form one contract party with the People’s Committee (PPP Law Art. 49.2). Strategic partners participate through capital contribution or share purchase in HEART HT, and the executed NDAs and letters of commitment remain effective, to be completed and supplemented before FS approval (Report 25/2026).
  • Acting ahead of approval. USD 50.0 m own budget deployed in 2026, of which USD 30.04 m is the full compensation, support and resettlement cost — borne entirely by the Investor inside the USD 315.3 m total investment, with no land-rent offset requested, preserving the project’s 100% private-capital character (Report 25/2026). The entire USD 50.0 m is contributed and disbursed as paid-in equity following completion of the charter-capital increase; debt is drawn only from 2027 after financial close.
Project structure — BOT single counterparty, two pillars
Project structure — BOT contract with a single signing counterparty to the People’s Committee; Pillar A (trunk infrastructure, PPP–BOT) and Pillar B (AI data center, Investment Law) kept strictly separate (FS Exhibit G-2).

15.4 Anchor pipeline and activation sequence

  • Target group. Six global neo-cloud providers (US GPU-export-approved), operators from the global top-10 data center group currently site-hunting in Vietnam, and six Anchor candidates (global big tech, HQ in the US and Asia–Pacific).
  • Current status (anonymised under NDA). KYC packs issued to prospective customers; NDAs signed with multiple parties; several parties in site due diligence; three of six Anchors have received site information over an extended period.
  • Majority-role screening. One major candidate in the power/energy sector oriented to a majority role in the power component, and one major candidate in the AI DC sector oriented to a majority role in the AIDC component, have been screened at central-government circulation stage. Both remain candidates; identities are withheld under NDA and may be replaced by third global operators.
Five-step activation sequence — triggered only once the national assurance framework is complete (Establishment Decision · PDP8 amendment update · state approvals for power/water/telecom)
StepContentActor
1Announcement of the Establishment Decision of the ParkHue City People’s Committee
2Anchor confirms investment intent — activation conditionGlobal technology group
3DEPC contractor and Operator formally register, meeting security · capital · technology · track-record requirementsInternational contractor / operator
4Invitation to ecosystem companies of the global technology group (excl. power – water – land – buildings)Coordinating investor
5Final investment decision — contract execution and capital contributionAll parties
Source. Report to the Chairman of the Hue City People’s Committee, September 2026, and Official Letter 17/2026/CV-HEART (investment commitment). By international practice, “contract first” does not exist in this market: contract and equity are the final step.

16Capital Structure — Pillar A and Pillar B

The project is capitalised in two separate pillars, with different balance sheets, different corporate vehicles, different investor sets and different procurement routes. Pillar A is the park’s shared trunk infrastructure, delivered under a PPP/BOT contract using no state capital. Pillar B is the AI data center itself, funded by the data center operator and its own capital stack, outside the PPP contract. Construction opportunity exists in both — but the contracting counterparty is not the same.

Pillar A versus Pillar B — structural comparison
DimensionPillar A — PPP/BOT trunk infrastructurePillar B — AI Data Center
Physical scopeSite formation, internal and external roads, power source, substations and HV lines, water supply, wastewater and large-scale cooling water, fibre and shared digital infrastructure, lighting, landscape and fire protection — across the whole 1,081 haData center core & shell, electrical and mechanical systems, liquid cooling plant and the IT hardware estate — inside PK-2 (319.52 ha)
CapitalUSD 315.3 m committed programme — compensation, support and resettlement included (Report 25/2026)Operator capital at hyperscale; ~1,000 MW target at full build
VehicleProject SPC under a BOT contract of 25–30 years; PPP Law No. 64/2020/QH14 as consolidated; no state capitalOperator or anchor-tenant balance sheet, co-development JV, or lease of powered land — commercial, outside the PPP contract
Capital sources100% private capital — equity ≥ 30% : debt ≤ 70%; no state capital in any form, no Government guarantee (Report 25/2026)Data center operator / anchor tenant / neocloud operator and its own lenders, sponsors and equipment financiers
ProcurementInvestor appointment under Articles 11(4) and 39(1)(đ) of the PPP Law; procedure per Article 27 of Decree 243/2025/ND-CPPrivate commercial procurement run by the operator on its own terms
Delivery interfaceOwner’s PM/CM, design and construction of the trunk works, staged GMP packages tied to the power gatesDesign-build or CM-at-Risk for the data center modules; specialist MEP and liquid cooling; repeat module delivery
Schedule driverPhase 1 power, main access road, water intake and trunk fibre — all must precede CODQ4 2027 COD for the first ~100 MW hall; subsequent modules follow the power tranches
Pillar A · PPP / BOT trunk infrastructure
USD 315.3 m

Committed programme, 100% private capital. Equity ≥ 30% of total investment (≥ USD 94.6 m — more than twice the statutory minimum), debt ≤ 70%, financial close within 12 months of contract signing, performance security 1–3%. No state capital in any form and no Government guarantee (Report 25/2026, §20.2).

Pillar B · AI data center
Operator capital

A separate project under the Investment Law, funded by the data center operator and its own capital stack, outside the PPP contract. Phase-2 reference scale USD 2,330 m (§15.3); ~1,000 MW target at full build. Investor incentives: §17.

Restricted disclosure — NDA + KYC counterparties only. The detailed capital structure — investment cost breakdown by heading, funding allocation, capital-raising plan and the data-center capital stack — is not published in this document. It is disclosed exclusively to counterparties that have executed the NDA and completed KYC, through the secured data room, on request via the engagement route in §21.

16.1 Why the two-pillar split matters commercially

  • Leverage sits in Pillar A. At approximately USD 300 million, Pillar A is around 2% of the capital stack it unlocks at the 100 MW module level — and a precondition for all of it. Power, water and fibre delivered on programme are what convert the site from land into contracted capacity.
  • Risk profiles differ. Pillar A carries land, permitting, utility-interface and long-tenor availability risk under a 25–30 year BOT. Pillar B carries technology-obsolescence, tenant-credit and utilisation risk on a much shorter asset life.
  • Contracting counterparties differ. A delivery partner may hold a role in one pillar, both pillars, or a coordinating role across the interface. The interface itself — where trunk infrastructure hands over to the data center module — is where most schedule risk concentrates.
  • Scale asymmetry is the negotiating fact. Ten modules at the 1,000 MW target imply a Pillar B stack roughly two orders of magnitude larger than Pillar A. The park’s value is not in its own CAPEX; it is in what that CAPEX makes buildable.

17AI DC Investor Incentives · Law 133/2025/QH15 · Decree 260/2026/ND-CP

An AI data center built inside the Hue High-Tech Park (Pillar B, §16) sits under the new high-tech regime in force since 1 July 2026 — High Technology Law No. 133/2025/QH15, Decree No. 260/2026/ND-CP, and the lists of strategic and high technologies (Decisions 21/2026/QĐ-TTg and 23/2026/QĐ-TTg). The regime works in layers: a location-based package that every new project in the park receives without any enterprise certificate; a treatment that the Law names specifically for AI data center projects; certificate-based upgrades that extend the preferential tax period to 25 years; and cost pass-through on land that is written into the park developer’s own obligations.

17.1 The incentive stack at a glance

Layer 1 · automatic, by location
10% × 15 yr

CIT at 10% for 15 years, 4 years exempt + 50% reduction for up to 9 more — for income from any new investment project in a high-tech park, regardless of enterprise certification (CIT Law 67/2025/QH15, Art. 13.1(d), 14.1(a)).

Layer 2 · named for AI data centers
Customs priority

Enterprises implementing AI data center construction projects are expressly listed as eligible for the customs priority regime, subject to the conditions of the Customs Law (High Technology Law, Art. 25.5).

Layer 3 · with a certificate
10% × 25 yr

A Group-1 high-tech enterprise, a strategic-technology enterprise or an R&D centre receives CIT at 10% for 25 years, plus import-duty, procurement and customs benefits (Art. 25 Law; Art. 17 Decree 260 — 5-year certificate).

Land · passed through
Full-term

The park developer is exempt from State land rent for the whole lease term on land subleased to high-tech / strategic-tech projects, and may not price the exempted rent into the sublease (Decree 260, Art. 23.5).

Fast track · one-stop
15 + 1 days

Where no investment-policy approval or IRC is required, the park Management Board appraises in 15 working days and issues the confirmation letter within 1 further working day (Decree 260, Art. 28.3, 31); one-stop / inter-agency handling of investment, land, construction, environment, labour, tax and customs procedures (Art. 22.2).

Talent · people
PIT · visas

High-tech personnel, including foreign nationals, receive personal-income-tax exemption as provided in the PIT law, plus training, housing and living-cost support; R&D staff receive entry, residence and work-permit preferences (Law, Art. 13.1, 16.2).

Headline CIT rate by year of taxable income — illustrative Yr 1514162630 Location regime any new project in the park 0% 5% (50% of 10%) 10% 20% standard Certified enterprise Group-1 HT / strategic-tech / R&D 0% 5% (50% of 10%) 10% 20% Reference no preferential regime 20% standard rate throughout Simple average of headline rate, years 1–30: Location regime ≈ 12.2%  ·  Certified enterprise ≈ 8.8%  ·  Reference 20%
Reading the chart. Durations are statutory maxima; the start of the exemption window follows the CIT Law. Averages are an arithmetic illustration of headline rates only — not an effective-tax-rate projection, and not tax advice. Where more than one preferential regime could apply, the investor should confirm with its tax adviser which single regime is elected.

17.2 Layer 1 — location-based package (no certificate required)

These apply to the AI data center project because it is located in the park. Projects in a high-tech park include projects under the Investment Law, public investment projects and PPP projects (Decree 260, Art. 3.7).

IncentivePosition for an AI DC investorLegal basis
Location statusProjects in the park receive the incentives and support applicable to areas with especially difficult socio-economic conditions — the most favourable location tier.Law 133, Art. 22.5(a); Decree 260, Art. 22.1
Corporate income tax10% for 15 years; exemption up to 4 years; 50% reduction up to the following 9 years — for income from a new investment project in the park, independent of any enterprise certificate.CIT Law 67/2025/QH15, Art. 13.1(d), 14.1(a)
Administrative procedureSupport for recruitment and for investment, enterprise, land, construction, environment, labour, tax and customs procedures on a one-stop / inter-agency one-stop basis, within the powers delegated to the Management Board by ministries and the City.Decree 260, Art. 22.2, 32, 33
Programmes & sandboxPriority access to State science-and-technology programmes on high and strategic technology, to controlled testing (regulatory sandbox), and to venture-capital funds — relevant to AI platform, sovereign-cloud and data-service pilots.Law 133, Art. 22.5(đ); Decree 260, Art. 22.3, 25.3
City-level supportThe City People’s Council may adopt its own support policies and levels for investment in the park.Decree 260, Art. 22.4

17.3 Layer 2 — the AI data center treatment and the eligibility pathway

Named in the Law

AI data center construction projects — customs priority regime

Article 25.5 of the High Technology Law extends the customs priority regime to high-tech and strategic-technology enterprises and, by name, to enterprises implementing AI data center construction projects, semiconductor-chip projects and key digital-technology product projects — provided the conditions of the Customs Law are met. For an AI campus whose capital stack is dominated by imported GPU/server estate, power and cooling plant, customs handling sits directly on the critical path to COD.

Project eligibility in the park

  • The project must fit the park’s mission and meet the general and type-specific criteria — R&D centre, incubator, or provision of high-tech / strategic-technology services, with the service on the applicable List (Decree 260, Art. 26).
  • The AI DC is positioned as technology infrastructure — computing and data infrastructure, digital platform and controlled test environment (§5). Mapping of the specific service lines to Decisions 21/2026 and 23/2026 is confirmed project by project.

Confirmation — how fast

  • Where the project does not require investment-policy approval or an IRC, the Management Board appraises within 15 working days of a complete dossier and issues the confirmation letter within 1 further working day (Decree 260, Art. 28.3, 31).
  • The confirmation letter is also the trigger for the developer to sublease the land (Art. 23.3) — see §17.5.

17.4 Layer 3 — certificate-based upgrades for the AI DC operating company

If the AI DC project company (or its R&D arm) obtains a confirmation as one of the enterprise types below, the location package is upgraded. Certificates are valid for 5 years (Decree 260, Art. 17).

Enterprise typeCITOther benefitsCriteria / conditions
Group-1 high-tech enterprise · strategic-technology enterprise · high-tech / strategic-tech R&D centre10% for 25 years; exempt up to 4 yr; 50% reduction up to 9 yr• Import duty exempt for 5 years on raw materials, supplies and components imported for production and research (Law, Art. 25.6); exempt on specialised equipment and supplies for high-tech / strategic-tech R&D (Decree 260, Art. 4.2(a), 5.2(a))
• Customs priority regime (Law, Art. 25.5)
• Procurement preference in contractor and investor selection; no obligation to prove equity (Law, Art. 25.3)
Quantitative criteria — Decree 260, Art. 15, 16. Strategic-technology enterprise: ≥ 51% domestic ownership, unless the Prime Minister decides otherwise (Law, Art. 15.6)
Group-2 high-tech enterprise10% for 15 years; exempt up to 4 yr; 50% reduction up to 9 yrDecree 260, Art. 14
High-tech product manufacturer17% for 10 years; exempt up to 2 yr; 50% reduction up to 4 yrSame import-duty, customs and procurement benefitsDecree 260, Art. 13 — typically less relevant to an AI DC operator
High-tech / strategic-tech R&D centre — landExempt from land rent for the entire lease termDecree 260, Art. 9.3(a)
Structuring point. Under the location package alone the CIT window is 15 years; a Group-1 or strategic-technology confirmation adds ten further years at 10%. The 51% domestic-ownership condition is stated for the strategic-technology enterprise route; the Group-1 high-tech enterprise route carries the same 25-year CIT treatment against its own quantitative criteria (Decree 260, Art. 15, 16) — the practical route for a foreign-majority AI DC operator. Joint-venture and co-development structures (§16) should be designed with this distinction in view.

17.5 Land, lease and cost pass-through

  • Who leases from whom. The AI DC investor subleases land from the park infrastructure developer (Decree 260, Art. 9.3(a)). The park is a no-State-budget park (§15.3, §16): the State leases the land to the developer, which subleases developed land; for projects that must meet the Art. 26 criteria, sublease follows the project’s confirmation letter (Art. 23.3).
  • Land rent exempted at developer level. After the construction-period exemption, the developer is exempt for the whole lease term on area subleased to high-tech and strategic-technology projects, and exempt for 15 years with a 50% reduction thereafter on other area (Art. 23.5).
  • Pass-through written into the rule. The developer may not include the exempted or reduced land rent in the sublease price (Art. 23.5), and the sublease price framework is registered with the Management Board (Art. 29.8). The AI DC tenant therefore does not carry State land rent on qualifying area.
  • Priority of law. Where high-technology law differs from land law, high-technology law prevails (Decree 260, Art. 44).
  • Tenure. The AI DC runs on a 50-year high-tech track (§1); Pillar B’s phase-2 reference scale is above the VND 30,000 bn special-incentive threshold of Art. 20 of the Investment Law (§15.3), which is a separate track.

17.6 Talent, R&D and financing support

People

  • High-tech personnel, including foreign nationals: PIT exemption as provided in the PIT law; support for training, housing and living costs under the employment contract (Law, Art. 13.1; Decree 260, Art. 35, 36).
  • R&D staff of high-tech / strategic-tech enterprises: preferences on entry, exit, residence and work permits (Law, Art. 16.2).
  • Leading strategic-technology experts: market-negotiated salary, bonus up to 6 months’ salary a year, PIT exemption — high-tech and strategic-tech enterprises may apply the same policy (Decree 260, Art. 37, 38).
  • Staff may rent housing outside the park and have purchase priority on indefinite contracts; temporary residence with family in on-park accommodation (Art. 24.3, 30).

R&D and financing

  • Up to 100% funding of State-commissioned high-tech / strategic-tech tasks (Decree 260, Art. 4, 5).
  • Interest-rate support for up to 5 years: 70% of interest, capped at 8% p.a., for high-tech; 100%, capped at 10% p.a., for strategic technology (Art. 4, 5).
  • High-tech / strategic-tech start-ups: 100% waiver of fees for national key laboratories for 3 years, 50% thereafter; priority access to venture capital (Art. 11.2).

17.7 Conditions, obligations and points to confirm

ItemPositionStatus
Commitment disciplineA project that breaches its commitments may lose the incentives (Decree 260, Art. 27.2); the developer may admit only projects meeting the Art. 26 criteria and must monitor and report to the Management Board (Art. 27.3(d)).Condition
Certificate termEnterprise confirmations run for 5 years and must be maintained against the quantitative criteria (Art. 17).Condition
Service-line mappingAI compute, cloud, data and platform services to be mapped to the Lists (Decisions 21/2026 and 23/2026) for the specific project.To confirm
Customs priorityNamed eligibility for AI DC projects; access depends on satisfying the Customs Law conditions.To confirm
Regime selectionWhere several CIT regimes could apply, the elected regime is confirmed with the tax authority and the investor’s adviser.To confirm
TransitionCertificates issued under Law 21/2008/QH12 remain valid, with their tax incentives, until expiry (Law 133, Art. 27; Decree 260, Art. 45.3).In force
Basis of this section. High Technology Law No. 133/2025/QH15 and Decree No. 260/2026/ND-CP (both effective 1 July 2026); CIT Law No. 67/2025/QH15 as amended by Art. 25.7 of Law 133; Decisions 21/2026/QĐ-TTg and 23/2026/QĐ-TTg. Compiled by HEART HT as an orientation for prospective AI DC investors. It is not legal or tax advice; availability of each incentive depends on the specific project, the enterprise’s confirmation status and the decisions of the competent authorities, and the legal texts govern.

18Delivery Structure — PPP / BOT

The construction, operation and transfer of the park’s technical infrastructure is to be delivered under a public–private partnership using a BOT contract of 25–30 years, financed entirely from non-budget sources. This is a PPP project using no state capital under Articles 70, 71 and 72 of PPP Law No. 64/2020/QH14 (as amended and consolidated at Document No. 81/VBHN-VPQH dated 26 March 2026). All capital is arranged by the private investor; no form of state capital is used.

18.1 Scope of the PPP project

The full set of shared technical infrastructure for the park (approximately 1,081 ha at Hung Loc Commune, per the approved plan):

  • Site formation, ground preparation and framework technical infrastructure
  • Internal road network and external traffic connections
  • Power supply — sources, substations and high-capacity transmission lines serving the data center load
  • Water supply, drainage and wastewater treatment; large-scale water supply and cooling systems
  • Telecommunications, multi-source multi-route fibre and shared digital infrastructure
  • Lighting, landscape, fire protection and other shared infrastructure per the master plan

18.2 Investment phasing under the contract

StageContent
Phase 1 (priority)Essential infrastructure to bring the AI data center zone and the first loads into operation — initial power source and supply, main traffic spine, water supply and cooling, and trunk fibre.
Phase 2 (expansion)Increase supply capacity — additional 500/220 kV substation and independent standby power source — and complete the park-wide technical infrastructure per the master plan.

Programme, scale and boundary of each phase are fixed in the feasibility study report and the project contract.

18.3 Procurement route

ElementPosition
Investment policy decisionNot required. As an investor-proposed PPP project using no state capital, the project is exempt under Article 11(3)(a) of the PPP Law.
Investor selectionInvestor appointment under the procedure in Article 11(4) of the PPP Law, in the case set out at Article 39(1)(đ) — “a project requiring accelerated delivery, promoting socio-economic development and safeguarding national interests, proposed by an investor and approved by the competent authority”.
Justification — scheduleTechnical infrastructure must complete in step with the AI data center to meet time commitments to the anchor tenant and hyperscale cloud provider, and to capture the regional competitive window for AI and data infrastructure investment.
Justification — socio-economicJob creation, formation of a high-tech ecosystem, socio-economic development of Hue City and the region, and attraction of high-quality FDI.
Justification — national interestThe project is strategic digital and AI infrastructure contributing to national data sovereignty, aligned with Politburo Resolution 57-NQ/TW dated 22 December 2024.
ProcedurePer Article 27 of Decree 243/2025/ND-CP dated 11 September 2025 and the process at Article 11(4) of the PPP Law: (a) investor submits a proposal with justification, feasibility study report, capability dossier and draft contract; (b) competent authority appraises the FS, approves the project and the appointment result; (c) contract signature and implementation.

18.4 Technical qualification requirements

The report states expressly that the park’s technical infrastructure directly serves high-tech operations and the AI data center and carries exceptional technical requirements: high-capacity, high-reliability power source and transmission with redundancy targeting N-2 and Rated-4 reliability; multi-source, multi-route, high-capacity fibre with uninterrupted redundancy; large-scale water supply and cooling; and other works to advanced technical standards. Because of this specialised technical character and the need for full coordination, the project requires an investor with the professional capability, track record and integrated solution to match.

Core technical conditions — fixed and non-negotiable. ① Absolute zero-inundation performance guarantee for the data center and technical platforms, on a 1/1,000-year extreme-flood design basis (HHFP-P1-RWS-003), delivered through four engineered layers — flood-relief canals, controlled cooling-water flow routing, the hydropower-dam-class Ta Trach dam upstream, and professional dam operation by the dedicated state-owned Ta Trach operator (§13.2) — flood immunity is a qualification condition of the works, not an option; ② power redundancy targeting N-2 and Rated-4 reliability from independent sources; ③ multi-source, multi-route fibre with uninterrupted redundancy; ④ large-scale water supply and cooling with dry-season assurance. Bidders and delivery partners are evaluated against these four conditions first.

19Market Context — AI Infrastructure Unit Economics

The following third-party market data points are provided as external context for the scale and revenue density of AI data center capacity. They are not project forecasts and do not form part of the establishment report.

Neocloud operator benchmarks — as reported in market commentary, 13 August 2026
MetricCoreWeaveNebius
Contracted power capacity1.85 GW (operating basis, year-end)5.0 GW (raised from 4 GW)
Annualised recurring revenueUSD 19.5 billion (year-end)USD 12–15 billion estimated year-end; USD 3 billion ARR passed as at end-June
AI data center revenue growth—+514% year on year
Annual contract value per MW≈ USD 10.54 million≈ USD 20 million average; recent contracts reported up to USD 40–50 million
Indicative payback≈ 3 years1–3 years, driven by the higher per-MW rate

19.1 Read-across

  • Per-MW annual contract value is the metric that determines whether AI data center capital is recoverable. At the reported USD 20 million per MW average, capacity is being contracted at roughly double the level of the earlier generation of operators.
  • Applied to the Hue programme purely as an order-of-magnitude reference, the ~1,000 MW AI data center target sits in a capacity band where operators are currently contracting multi-billion-dollar annual revenue. The determining constraints are the ones this document sets out: power at scale, water at scale, diverse fibre, and schedule certainty.
  • This is precisely why the master plan treats the AI data center as the anchor and sizes the 500/220 kV head-end, the 100,000 m³/day water strategy and the Rated-4 connectivity around it, rather than the reverse.
Caveat. The figures in §19 are third-party market reports relayed in a broadcast dated 13 August 2026 and have not been independently verified. They are included for market framing only and carry no representation as to the project’s own returns.

20Approvals & Execution Status — Systematic De-risking

20.1 Register — current evidenced position

Every material item on the programme is identified, owned and moving. The September 2026 filings advanced the register decisively: the grid-connection dossier and the PDP8 pre-feasibility dossier are on file, water and carrier confirmations are in writing, and the 2026 budget is committed. The table below states each item and its current, evidenced position — and the thirteen standing commitments in §20.2 are what convert this register into an accelerable programme.

ItemStatusCurrent position — evidence on file
City leadership alignmentAffirmedAt the Chairman’s working sessions of 14 and 16 Sep 2026 (Invitation 936/GM-UBND) the Chairman of the People’s Committee concluded that the project is consistent with the orientation of the Party and the State, and that the City will work with the ministries and issue the decision selecting a fully capable, fully qualified investor. The Investor’s consolidated response is on file as Report 25/2026/BC-HEART (18 Sep 2026).
PDP8 amendment — 500/220 kVDossier filedThe pre-feasibility dossier for two 500/220/110 kV substations and 500 kV tie-lines was filed on 11 Aug 2026 per MOIT appraisal criteria (Official Letters 14/2026 and 18/2026/CV-HEART), and the project is carried on the City’s priority grid list (150 MVA 2026–2030 · 1,400 MVA 2031–2035). EVNCPC identified this as the key item for large secondary investors, and the Investor has proposed to fund both 500 kV substations itself. See §7.6, §8.2.
Phase-1 power configurationFiled · Rated-4The 22 kV connection dossier was submitted 28 Aug 2026: 40 MW from two independent 110 kV substations, each registered for the full load — 100% mutual backup over physically separate corridors. The temporary-supply plan is agreed with Hue PC and EVNCPC, and the load-commitment package (take-or-pay on registered capacity, bank guarantee/LC, staged BESS) is on file as CV 24/2026. Supersedes the earlier shared-segment concept. See §8.1, §8.3.
Chan May 220 kV upgradeScheduledTwo 250 MVA units are envisaged to 2030 and the project sits on the City’s priority grid list; connection-demand registration with EVN / EVNNPT runs in parallel with the dossier already filed. See §7.5.
Aviation corridorIn coordinationFlight-path coordination with the aviation authority is in progress; PK-2’s 319.52 ha gives generous siting flexibility for data-hall placement while coordination concludes.
Water — volume and deliverySecuredThe full 100,000 m³/day demand sits inside the existing 172,800 m³/day licence with a project-specific written confirmation (2744/SNNMT-TN); the delivery works — intake, transmission main, Ben Van storage and the Truoi redundancy link — are scoped in the FS, and on 16 Sep 2026 the reservoir operator confirmed the minimum regulated flow of ~150,000 m³/day secures the full requirement. See §9.
Statutory approvalsOn scheduleProvincial plan (A1) — complete. Establishment scheme (A2) — in appraisal. Establishment scheme circulated to four ministries for opinion by the City on 24 Jul 2026 (11067/UBND-KHCN). For the 1/2,000 zoning plan (A3), the Investor has proposed — and committed funding for — preparing the Phase-1.1 zone plan under City assignment, holding the 2026 / early-2027 start; the phasing petition was filed 26 Aug and the FS authorisation letter has been requested. See §15, §20.2.
Land & resettlementFunded & phasedDelivery follows the 40/30/30 phasing plan with USD 50.0 m own budget committed for 2026, including the USD 30.04 m compensation, support and resettlement cost borne entirely by the Investor with no land-rent offset requested. ~180 households, low settlement density — among the most straightforward land positions of any Vietnamese HTP. See §15.
Carrier-neutral Meet-Me RoomCarrier-backedViettel and VNPT have both confirmed capability in writing (Letters 705 and 1028) with survey and detailed-design commitments; the MMR is programmed live at least three months before COD. See §11.
UXO & earthworksBudgetedVND 15 bn for UXO clearance and VND 200 bn for site formation are carried in the CAPEX; the 12.1% of the site below 10 m is reserved for landscape and water use, outside the platforms.

20.2 Thirteen standing commitments of the Investor — Report 25/2026

Commitments tabled to the Chairman of the People’s Committee, 18 Sep 2026 (Section V, Report 25/2026/BC-HEART)
No.CommitmentBasis
1100% self-arranged capital for the full USD 315.3 m; no state capital (PPP Law Arts. 70, 72); no Government guaranteeCV 17/2026
2Equity ≥ 30% of total investment (≥ USD 94.6 m — more than twice the 15% legal minimum); debt ≤ 70%; financial close within 12 months of contract signingCV 17/2026 · PPP Law Arts. 76–77
3Performance security of 1–3% of total investment, independent of project investment outlaysCV 17/2026 · PPP Law Art. 48
4USD 50.0 m own equity deployed in 2026 / early 2027, ahead of financial close — including USD 30.04 m compensation, support and resettlement borne entirely by the Investor, no land-rent offset requestedCV 17/2026
5Self-funded grid works, handed to EVNNPT on completionCV 24/2026
6Minimum take-or-pay on registered capacity of each phase (orientation 60–70%), independent of actual usage; two-part tariff; bank guarantee / letter of creditCV 24/2026
7Four-layer oscillation absorption and staged BESS; each load step starts only after the previous step passes grid-impact verificationCV 24/2026
8No tolls on the expressway connection; ready to build the interchange directly (or jointly) and hand it to the localitySession of 16 Sep 2026
9100% of the ~60 km internal road network at Investor costBC 23/2026
10Replacement-forest payment for the converted forest area, per regulationBC 23/2026
11Cooperation with Hue University and training institutions on AI and semiconductor talent, to international data-center operations standardsSession of 16 Sep 2026
12Financial-capability dossier (post-increase equity and allocations for land clearance, substations and roads) submitted before FS approvalReport 25/2026
13Preparation and funding of the Phase-1.1 zone 1/2,000 plan, if assigned by the People’s CommitteeReport 25/2026
Reading this register. These are the items an experienced delivery partner engages with first — each arrives with a filed dossier, a written confirmation or a committed budget behind it. Together with the commitments above, they are why the Investor treats the roadmap not as a ceiling but as a floor: early build-out is pursued wherever State and city objectives allow.

21Indicative Delivery Partner Scope and Next Steps

This section is indicative and for discussion. It sets out where international construction and programme management capability maps onto the delivery structure described above.

21.1 Where the delivery challenge sits

Schedule is the binding constraint

Phase 1 COD is Q4 2027 at 150 MW, with the Meet-Me Room live three months earlier. Anchor-tenant commitments run off that date. The critical path is head-end power, the main access road, water intake and trunk fibre — all in the PPP scope.

Modular repeatability

PK-2 is designed as parallel low-rise modules on 319.52 ha, expanding from ~100 MW to ~1,000 MW. Value comes from a repeatable module design, a standing supply chain and parallel commissioning — not from one-off construction.

Specialist building types in PK-1

Class 100–10,000 cleanrooms, UPW plant, chemical distribution, GMP-WHO pharmaceutical areas and vibration-sensitive laboratories on 272.07 ha, including the 289.4 ha pilot production programme.

Flood immunity is contractual

Drainage and earthworks are designed against the 1/1,000-year extreme flood (HHFP-P1-RWS-003), and the delivery scope carries an absolute zero-inundation performance guarantee for the data center platforms as a core technical condition (§18.4), backed by the flood canals, controlled cooling-water routing, the hydropower-dam-class Ta Trach dam and its professional state-owned operator (§13.2). Flood-relief channels, platform levels and outfall works sit on the Phase-1.1 critical path.

Heavy MEP and utilities

A 3 × 900 MVA 500/220 kV station in transit connection, a 2 × 250 MVA 220/110 kV receiving station feeding HTZ-SS1–SS3, temporary 22 kV works on two corridors, liquid cooling at rack level, a 100,000 m³/day water and cooling system and a closed-loop wastewater plant — all to N-2 and Tier III/IV.

21.2 Candidate roles for discussion

  • Programme management / owner’s representative across the PPP trunk-infrastructure scope, interfacing EVN, the water authority, VNPT/Viettel and the Management Board
  • Design-build or construction management for the PK-2 AI data center modules, including a standard module design set for repeat delivery
  • Specialist MEP delivery — HV substations, liquid cooling systems, ultrapure and cooling water plant
  • Cleanroom and process facility delivery in PK-1, including the semiconductor pilot line and GMP-WHO pharmaceutical facility
  • Feasibility study and contract support — the investor-appointment route requires an FS report, capability dossier and draft project contract, where demonstrated international delivery capability directly supports the appointment justification set out in §18.3

21.3 Proposed next steps

  1. Technical workshop on the Phase 1 150 MW package — scope split between EVN works, PPP works and tenant works
  2. Site visit to Hung Loc, including the 500 kV corridor, the Ta Trach intake location and the Step 1 200 ha parcel
  3. Schedule review against the Q4 2027 COD, identifying long-lead items — HV transformers, switchgear, cooling plant
  4. Commercial framework discussion — role within the BOT structure, and the interface with the anchor tenant’s own delivery programme
  5. Release of the detailed technical annexes — master plan drawings, single-line diagrams, geotechnical survey and the full establishment report — under the executed NDA
Contact. HEART High-Tech Joint Stock Company (Cong ty Co phan Cong nghe cao HEART HT) — project sponsor for the Hue High-Tech Park programme. All technical annexes referenced above are available on request under the executed NDA.

◉Site Survey

On-the-ground photographic survey of the HEART project site and its immediate surroundings, captured during field visits. Click any photograph to enlarge.

HEART site survey photograph 1 of 12 HEART site survey photograph 2 of 12 HEART site survey photograph 3 of 12 HEART site survey photograph 4 of 12 HEART site survey photograph 5 of 12 HEART site survey photograph 6 of 12 HEART site survey photograph 7 of 12 HEART site survey photograph 8 of 12 HEART site survey photograph 9 of 12 HEART site survey photograph 10 of 12 HEART site survey photograph 11 of 12 HEART site survey photograph 12 of 12
12 field photographs · source: HEART Project site survey.
HEART HT
HEART High-Tech Joint Stock Company CÔNG TY CỔ PHẦN CÔNG NGHỆ CAO HEART HT Enterprise Code 0315738961 · Socialist Republic of Viet Nam heartproject.vn
Document
HEART-ALL-CON-BRF-001-RevD — HEART Project · Hue High-Tech Park · Infrastructure Overview
Issued to
Prospective delivery partner — named recipient
Issue date
13 August 2026
Classification
Strictly Confidential — released under NDA
Controlling doc
DT_BCTH_DeanKHCNHue, 12 July 2026
The Important Notice and Disclaimer set out in this document applies to its entire contents and is incorporated here by reference. Recipients are reminded that this document is provided under an executed Non-Disclosure Agreement and may not be distributed, reproduced or extracted in any form.
© 2026 HEART High-Tech Joint Stock Company. All rights reserved.
Strictly Confidential · AES-256-GCM · Do Not Distribute
×
‹
Site survey photograph — enlarged
›